Permit Information
Permit NumberESC08-00894
StatusFinaled
Name JAMES LARKIN
Site Address 554 S BLUE PINE LN
Project NamePinetree Village
Customer Number 
ePlanReview 
Description
Unit 1 Building 14
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled6/4/20096/4/20096/4/2009PPASS
DetailsClint A Smith
Random Inspection4/21/20094/21/20094/21/2009PPASS
DetailsMike Jordan
General Inspection4/6/20094/6/20094/6/2009PPART
DetailsSteven Webb
Verbal to rp; need gutters cleaned, trash management and mortal mix covered
Random Inspection3/18/20093/18/20093/18/2009PPASS
DetailsMike Jordan
BMP Violation3/13/20093/13/20093/13/2009APASS
DetailsMike Jordan
General Inspection3/11/20093/11/20093/11/2009PPART
DetailsMike Jordan
Nees to clean up const. debries, sweep al sediments from street, sidewalks and gutterpan.
General Inspection3/9/20093/9/20093/9/2009PPASS
DetailsBob Reichert
looked ok
BMP Violation2/23/20092/23/20092/23/2009PPASS
DetailsMike Jordan
BMP Violation2/20/20092/20/20092/20/2009PPART
DetailsMike Jordan
Significant progress has been made on cleanup. Needs to cleanup all const. debries.
BMP Violation2/19/20092/19/20092/19/2009PFAIL
DetailsMike Jordan
Needs to sweep all sediments from street, sidewalks and gutterpan.
Tracking Control2/18/20092/18/20092/18/2009PPART
DetailsMike Jordan
Track out is minimal, contractor is sweeping on daily basis and as needed.
Tracking Control2/17/20092/17/20092/17/2009PPASS
DetailsMike Jordan
New BMp's installed per revised and approved ESC plan. Trackout is minimal, contractor is sweeping daily and as needed.
Random Inspection2/11/20092/11/20092/11/2009APASS
DetailsMike Jordan
Random Inspection2/10/20092/10/20092/10/2009PPASS
DetailsMike Jordan
Random Inspection2/3/20092/3/20092/3/2009PPASS
DetailsJim Johnson
sign posted stockpiles created bywater and sewer excavation have been removed additional exteral protection on storm drain,s have been intsalled
BMP Violation1/27/20091/29/20091/29/2009APART
DetailsClint A Smith
Verbal to RP:
They are in the process of backfill trenches and removing the stock piles. Activily placing exteral protection on storm drains and maintain all protection on all of them through the construction project area. Told RP to clean up all sediment and debris off of all hard surfaces at the end of the work day or if it gets to excessive. Will re-inspect the sud-division 2/2/09. Refer to ESC08-00706. Will input if pertaining to a single lot though.
BMP Violation1/27/20091/27/20091/27/2009PFAIL
DetailsClint A Smith
Left the message of the C/N with the RP
Correction Notice:
1.Clean all hard surfaces of all sediment and debris.
2. Install temporary protection on stockpile that will pervent erosion from occuring.
3.Install external storm drain protection surrounding the inlet. Will not except wattle that is not weighted.
Failure to comply will result in a stop work order. Will re-inspect on 1/29/09 AM.
Site Preparation1/22/20091/22/20091/22/2009PPASS
DetailsMike Jordan
ESC permit signposted. ok.
Site Preparation1/21/20091/21/20091/21/2009APART
DetailsMike Jordan
Conc. washout in place. BMP's in place. Gave RP verbal c/n to post ESC signs. Will reinspect tomorrow.
Issue & PRINT permit SFD  1/20/2009 DONE
DetailsBarbara Stitt
Application received  10/14/2008  
Routing - Erosion and Sediment     
DetailsSteven Webb