Site Final | 9/1/2009 | 9/1/2009 | 9/1/2009 | P | PASS |
Mike Jordan
|
|
|
Final stabalization has been completed.
|
Random Inspection | 6/19/2009 | 6/19/2009 | 6/19/2009 | P | FAIL |
Tom Arcoraci
|
|
|
incomplete
|
General Inspection | 5/18/2009 | 6/18/2009 | 6/19/2009 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: obtain permit for the area to the east of project where stockpile of materail and debris. Must be complete by 6/24/09PM. Will re-inspect on 6/25/09AM.
|
Random Inspection | 6/18/2009 | 6/18/2009 | 6/18/2009 | P | PART |
Tom Arcoraci
|
|
|
clean up debris
|
Random Inspection | 6/5/2009 | 6/5/2009 | 6/5/2009 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/27/2009 | 5/29/2009 | 5/29/2009 | A | PASS |
Clint A Smith
|
|
|
|
Random Inspection | 5/27/2009 | 5/27/2009 | 5/27/2009 | P | FAIL |
Clint A Smith
|
|
|
Message to RP: Correction Notice; 1. Clean all hard surfaces of ALL sediment and debris. 2. Consolidate all wood spoils into one pile. Not scattered throughout project area. 3. Maint or remove all siltfence along the front of project area. 4. Provide a washout pit prior to anymore concrete or mortar work and post signage. Failure to comply within the given time frame will result in a stop work order. Will re-inspect on 5/29/09AM.
|
Tracking Control | 5/18/2009 | 5/18/2009 | 5/18/2009 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: 1. Clean up all trackin onto street where gravel fill is being brought in. This will be the last day of flat work.
Also discussed with RP over stabilizing stock piles on lot to the east. If stockpiles are sitting for more than 30 days temporary stabilized or not, a permit is required. RP is waiting on the go on a duplex unit on that lot. So I have given the ok for 30 days or until permit is issued for the duplex unit. Will re-inspect on this issue on 6/18/09.
|
BMP Violation | 5/12/2009 | 5/15/2009 | 5/18/2009 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/8/2009 | 5/12/2009 | 5/12/2009 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Re-install silt fence along the front of the project area. Provide a trash container for all trash debris generated from construction. Clean up all hard surfaces of all seiment and debris on a daily basis. Will re-inspect on 5/15/09PM.
|
Site Preparation | 4/29/2009 | 4/29/2009 | 4/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
Issue & PRINT permit SFD | | | 4/21/2009 | | DONE |
|
|
|
|
Application received | | | 3/10/2009 | | |
|
|
|
|