Aging Inspection | 11/26/2010 | 11/26/2010 | 11/26/2010 | | DONE |
Clint A Smith
|
|
|
|
DOC - Permit Finaled | 11/26/2010 | 11/26/2010 | 11/26/2010 | P | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 1/20/2010 | 1/25/2010 | 1/25/2010 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection | 1/20/2010 | 1/20/2010 | 1/20/2010 | A | FAIL |
Clint A Smith
|
|
|
Verbal to GC: Replace the sediment barrier along the front of lot behind the back of sidewalk. Also to provide a valid RP for the ending duration of the project. Will re-inspect on 1/25/10am.
|
BMP Violation | 9/29/2009 | 10/1/2009 | 10/1/2009 | A | PART |
Clint A Smith
|
|
|
Wattle installed but needs to be placed back into place at the end of the work day.
|
BMP Violation | 9/25/2009 | 9/29/2009 | 9/29/2009 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice: Install perimter barriers along the perimeter slopes along the sidewalk. Will re-inspect on 10/1/09
|
Complaint Inspection | 9/25/2009 | 9/25/2009 | 9/25/2009 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: 1. Re-install sediment barriers along the perimeter of slope. 2. Replace the D.I. protection to the north of the project area. Will re-inspect on 9/29/09AM.
|
Random Inspection | 9/4/2009 | 9/4/2009 | 9/8/2009 | P | PART |
Tony Young
|
|
|
cleaning up,, wip
|
General Inspection | 9/3/2009 | 9/4/2009 | 9/8/2009 | A | PART |
Tony Young
|
|
|
wip,, fixing BMPs,, landscaper coming in on 8th
|
General Inspection | 9/3/2009 | 9/3/2009 | 9/3/2009 | P | FAIL |
Doug A Poedy
|
|
|
Trash and debri, Needs hard surfaces sweep. Pick up bad woddles.
|
Random Inspection | 8/20/2009 | 8/20/2009 | 8/20/2009 | P | PASS |
Daryl Spivey
|
|
|
|
Random Inspection | 7/27/2009 | 7/27/2009 | 7/27/2009 | P | PASS |
Daryl Spivey
|
|
|
sign in place and no trash......ds
|
Random Inspection | 7/1/2009 | 7/1/2009 | 7/2/2009 | P | PASS |
Tony Young
|
|
|
|
General Inspection | 6/30/2009 | 6/30/2009 | 6/30/2009 | P | PART |
Bob Reichert
|
|
|
called to install sign at front of property, talked with rp, will fix in am, rest appeared ok
|
Site Preparation | 6/3/2009 | 6/3/2009 | 6/3/2009 | | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Re-install wattle per industry standards. Post ESC sign at the front of project. Will re-inspect on 6/8/09.
|
Site Preparation | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | PASS |
Tony Young
|
|
|
BMPs in place
|
Site Preparation | 5/28/2009 | 5/28/2009 | 5/28/2009 | A | FAIL |
Tony Young
|
|
|
BMPs not in place but working on
|
Issue & PRINT permit SFD | | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions.
|
Application received | | | 4/7/2009 | | |
|
|
|
|