Permit Information
Permit NumberESC09-00160
StatusFinaled
Name BRANDON L WALKER
Site Address 4450 N FIVE MILE RD
Project NamePriest Retirement House
Customer Number 
ePlanReview 
Description
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final2/17/20102/17/20102/17/2010PPASS
DetailsJim Sly
DOC - Permit Finaled2/17/20102/17/20102/17/2010PPASS
DetailsJim Sly
Site Final2/17/20102/17/20102/17/2010PCANC
DetailsJim Sly
Brandon W
Random Inspection2/1/20102/1/20102/1/2010PDONE
DetailsClint A Smith
Left message for RP to contact me over pulling out the storm drain inlet protection so a Site Final can occur. Waiting on a call back.
Random Inspection11/18/200911/18/200911/18/2009APART
DetailsClint A Smith
Verbal to RP:
Protect stock piles of bark and top soil with using a plastic tarp. Will follow up on 11/19/09 PM.
Tracking Control11/3/200911/5/200911/5/2009APART
DetailsClint A Smith
Waiting on a street sweeper tonight to finish up the clean up efforts.
General Inspection11/3/200911/3/200911/3/2009AFAIL
DetailsClint A Smith
Message to RP:
Clean up roadway of all sediment from where landscaping occured. Will re-inspect on 11/5/09AM
General Inspection10/15/200910/16/200910/16/2009APART
DetailsClint A Smith
Verbal to RP:
Clean up areas where paint and plaster washout has occured. Place it into the washout pit. Correct by instructing the crew where has needs to occur.
Random Inspection10/6/200910/6/200910/6/2009PPASS
DetailsClint A Smith
General Inspection9/16/20099/16/20099/17/2009PPART
DetailsJim Sly
Brandon phone
Talked to RP.....sweep all hard surfaces.
BMP Violation9/4/20099/8/20099/8/2009APART
DetailsEric Strole
sod will be installed by weeks end, working on silt fence silk.
General Inspection8/31/20099/4/20099/4/2009AFAIL
DetailsEric Strole
left verbal & written correction with rp to protect stock pile on south side of project & all slopes over 2 percent grade. maintain silt fence along five mile. clean dirt & debris off all hard surfaces. need to be complete by 9-6-09 or a stop work may be issued. will reinspect 9-8-09.
General Inspection9/2/20099/2/20099/2/2009PPASS
DetailsJim Sly
Stucco Contr. Complying with previous corr.
General Inspection9/1/20099/2/20099/2/2009ACANC
DetailsJim Sly
Re-Sched for PM...........
Site Preparation9/1/20099/1/20099/1/2009PFAIL
DetailsJim Sly
Brandon phone
Notified RP that Masonry Contr. mixing mortar without proper containment ie.....lined box. Will check back on 9/2/09 AM
BMP Violation8/28/20098/31/20098/31/2009PPART
DetailsEric Strole
di protection in place, will be removing stock pile & grading so not to be over 2 percent grade on site. will reinspect 9-04-09.
General Inspection8/24/20098/28/20098/28/2009AFAIL
DetailsSteven Webb
Correction Notice to RP:
1. Protect all storm drain inlets within the project area with an approved storm drain inlet protection.
2. Provide a sediment a barrier along the stock pile at the south end of project area and also on all grade over 2% slope including the the area where the grade is over the elevation of the hard surfaces. 3. Clean up all hard surfaces ofall sediment and debris.
Failure to comply will result in a stop work order. Will be re-inspected on 8/31/09 PM.
Conference8/21/20098/24/20098/24/2009ADONE
DetailsClint A Smith
Went over the phase of the project with the RP. Allowing that filt ter fabric be allowed within the storm drain inlet on the interior of the project during the time of paving occurs. Once paving is complete and cured, that an approved storm drain inlet protection is required. At the lasted of 8/27/09, all storm drain inlets must be protected with an approved method.

Told the RP that he must comply with federal regulations per the CGP and make sure that he can generate the narritive of his ECS plan on 8/28/09 AM. Will re-inspect on 8/28/09 AM.
Tracking Control8/19/20098/21/20098/21/2009AFAIL
DetailsClint A Smith
Most of the tracking was cleaned up.

Verbal to RP:
Clean up all mortor residual off of the ground and place it into the washout that was provided.
Maintain all storm drain inlets within project area.
Clean up all tracking off of the hard surfaces.
Will be having a confrence with the RP on 8/24/09 AM.
General Inspection8/21/20098/21/20098/21/2009PDEFR
DetailsJim Sly
Brandon phone
Defer to Clint....
Tracking Control8/19/20098/19/20098/19/2009PFAIL
DetailsClint A Smith
Verbal to RP:
Clean up all tracking coming off of both entrances where tracking has occured. Will re-inspect on 8/21/09am.
Random Inspection8/7/20098/7/20098/7/2009PPASS
DetailsClint A Smith
BMP Violation7/16/20097/21/20097/21/2009AFAIL
DetailsClint A Smith
Issued on the canal have been taken care of.
Verbal to RP:
Clean up all sediment and debris off of all hard surfaces with the drive way and Five Mile Rd.
Extend the construction exit to a 50ft min on the exit to the west.
General Inspection7/16/20097/16/20097/16/2009AFAIL
DetailsClint A Smith
Verbal to Assistant(Kevin), RP off of work today:
If stockpile are not back filled by 7/20/09PM, Will require to install sediment barriers along the canal to the east of project.
Also clean up all tracking onto drive to the east and west. Will reinspect on 7/21/09 AM.
General Inspection7/7/20097/7/20097/7/2009PPASS
DetailsJim Sly
Brandon Phone
Site Preparation6/30/20096/30/20097/1/2009APASS
DetailsJim Sly
Site Preparation6/26/20096/26/20096/26/2009PPASS
DetailsJim Sly
Site Preparation6/23/20096/23/20096/23/2009PPART
DetailsJim Sly
Need Concrete washout pit.
Site Preparation6/18/20096/18/20096/18/2009 PASS
DetailsClint A Smith
Informed RP to keep any eye on your dust issues.
Site Preparation6/11/20096/12/20096/12/2009APART
DetailsClint A Smith
Verbal to RP:
Provide a washout with a sign posted at the location. Must occur prior to the pour of any concrete.
Issue & PRINT permit COM  6/11/2009 DONE
DetailsTisha Gallop
INSP - Stop Work Order5/11/20095/11/20095/11/2009PFAIL
DetailsClint A Smith
Started to clear and grub project area prior to permit being issued. Doulbe fee on ESC permit.
Routing - Erosion and Sediment4/17/2009 4/17/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions.
Application received  4/8/2009