Permit Information
Permit NumberESC09-00164
StatusFinaled
Name SCOTT P FREEMAN
Site Address 1000 N AMERICANA BLVD
Project Name 
Customer Number 
ePlanReview 
Description
Irrigation sand removal project-Ann Morrison Park
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final7/15/20099/15/20099/15/2009PCANC
DetailsSteven Webb
Already finaled
Site Final8/11/20098/11/20098/11/2009PPASS
DetailsClint A Smith
DOC - Permit Finaled8/11/20098/11/20098/11/2009PPASS
DetailsClint A Smith
Site Final7/22/20097/22/20097/22/2009PNR
DetailsClint A Smith
Site Final7/15/20097/15/20097/15/2009PFAIL
DetailsClint A Smith
Need to see growth on all disturbed areas and all temporary BMP's also must be removed before site can be finaled.
Random Inspection6/25/20096/25/20096/25/2009PPART
DetailsClint A Smith
Went over it will take to final out the ESC permit with the city. Waiting on a hydro-seeding application to occur on the area what the sand traps have been installed. A sediment barrier is still inplace for protection.
Random Inspection6/24/20096/24/20096/24/2009PCANC
DetailsSteven Webb
Entered wrong permit number.
General Inspection6/23/20096/23/20096/23/2009PPASS
DetailsSteven Webb
Slope has been graded. Sediment barriers are now below water level. Needs to be re-vegetated. Not ready for final.
Random Inspection6/1/20096/1/20096/1/2009PPART
DetailsSteven Webb
Overall site looks good, maintance on sediment barriers along the river edge is needed. Vaults have been backfilled but slopes are still bare. De-watering channel has been removed.
General Inspection5/20/20095/26/20095/26/2009ADONE
DetailsClint A Smith
General Inspection5/20/20095/20/20095/20/2009PPASS
DetailsClint A Smith
All discharging has completed. Now clean will occur and preparing area for stabilization. Recommended to the RP that hydroseeding would be the best option for stabilizing stream bank. Will re-inspect on 5/26/09 am.
General Inspection5/18/20095/18/20095/18/2009PPASS
DetailsClint A Smith
Dischaging into the park. Has not reached the boise river. Water is not turbid.
General Inspection5/15/20095/15/20095/15/2009APASS
DetailsClint A Smith
Discharging into the the park today. Water has not reached the river. but water is not turbid though.
General Inspection5/14/20095/14/20095/14/2009PDONE
DetailsClint A Smith
Deverting pumps to the river once the sediment within the sand trap pit settles out to discharge clean water back into the Boise River.
Random Inspection5/14/20095/14/20095/14/2009PDONE
DetailsClint A Smith
Went over with RP to keep an eye on all discharge points due to the turbid water reaching the north end of the Boise River. If the turbid water reaches the river to stop all deeatering and maintain the channel and free it of all sediment and debris prior to the start of dewatering again.
Random Inspection5/11/20095/11/20095/11/2009PPART
DetailsBill VanDegrift
pumping clean water
General Inspection5/6/20095/8/20095/8/2009ADONE
DetailsClint A Smith
Discharging clean water directly into the Boise River.
General Inspection5/7/20095/7/20095/7/2009APASS
DetailsSteven Webb
Dewatering was not occurring during inspection and no water was in the basin area. No runoff into the river. Vaults are set in place. Clean water was being directly discharged into the river since excavating was not being performed.
Random Inspection5/4/20095/4/20095/4/2009APART
DetailsBill VanDegrift
just getting started for the day
General Inspection4/30/20095/1/20095/1/2009ADONE
DetailsClint A Smith
Spoke with RP over issues that can not occur. " No discharging of TURBID water into the Boise River". Also told the RP to keep an eye on all discharge points into the River. As of 3:00 pm on 5/1/09 there are four.
Pumps will be running trough out the weekend. But was told that no excavating will occur this wekend from 5/2/09 to 5/3/09. Will begin to set sand traps on Monday 5/4/09. Will re-inspect on 5/4/09 AM
Conference4/30/20095/1/20095/1/2009ADONE
DetailsEric Strole
Conference4/30/20094/30/20094/30/2009ACANC
DetailsEric Strole
General Inspection4/30/20094/30/20094/30/2009AFAIL
DetailsClint A Smith
through out the day pumping has occured and the turbid water has been flowing into the grass area of the park. But through the duration of the day the water has migrated back to the river. Since the sediment dis not has a sufficent amount of time to drop and settle with the grassy area, it had reached the river at a further point and was discharging turbid water. Steve Webb instructed the company to shut the pumps off and to re stratigize to figure out a method that will not dischage turbid water into the Boise river.
Site Preparation4/30/20094/30/20094/30/2009PFAIL
DetailsSteven Webb
Observed minor volume of turbid water being discharged into the Boise River. Contractor shut off dewatering activities. Instructed RP that no turbid discharges can occur into the river or MS4 system. Also discussed with Parks, (Maria). Inspector 460 will follow up on 5/1/09.
Conference4/30/20094/30/20094/30/2009APASS
DetailsBill VanDegrift
with steve and clint
Site Preparation4/29/20094/29/20094/29/2009PCANC
DetailsClint A Smith
Routing - Erosion and Sediment4/29/2009 4/29/2009 PASS
DetailsSteven Webb
Received addendum report for dewatering process. Lifted stop work with condition to contact inspector 460 to inspect dewatering channel prior to starting up dewatering.
Random Inspection4/27/20094/27/20094/28/2009PFAIL
DetailsClint A Smith
STOP WORK ORDER.
INSP - Stop Work Order4/28/20094/28/20094/28/2009PFAIL
DetailsClint A Smith
Discharging Turbid water into the Boise River.
Contractor must re-submitt the "De- watering" plan to the city of Boise once the ammendment has been made. The stop work order will be pulled if the next plan does not allow turbid water into the Boise River.
General Inspection4/21/20094/23/20094/23/2009APASS
DetailsClint A Smith
No activity
Site Preparation4/21/20094/21/20094/21/2009 DONE
DetailsClint A Smith
Duplicate.
Site Preparation4/21/20094/21/20094/21/2009 PART
DetailsClint A Smith
Verbal to RP:
Post ESC sign on the temporary fence.
Also instructed RP to contact us prior to any dewatering. Will re-inspect once work occurs via RP's phone call
Routing - Erosion and Sediment4/13/2009 4/14/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions.
PLANS/APPL TAKEN TO FRONT DESK  4/14/2009  
Telephone call  4/14/2009 DONE
DetailsAlexandra L. DeYoung
Permit ready fees already paid
Permit Ready to Issue  4/14/2009 DONE
DetailsAlexandra L. DeYoung
Issue & PRINT permit COM  4/14/2009 DONE
DetailsBarbara Stitt
Telephone call  4/13/2009 DONE
Actually received plan resubmitals-2 copies of new narrative and taken to ESC inbox///4-13-09 @ 4:30pm BAS
Routing - Erosion and Sediment4/10/2009 4/10/2009 FAIL
DetailsSteven Webb
ESC plan needs dewatering details. Talked to RP (Scott Freeman) from M. R. Miller. He will submit the dewatering plan under the ESC Permit number when ready. PLAN IS LOCATED IN ESC PENDING BOX WAITING ON RE-SUBMITTAL
Application received  4/9/2009