Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberESC09-00365
StatusFinaled
Name MIKE SHAIN
Site Address 4610 W HILLCREST DR
Project NameHillcrest Country Club
Customer Number 
ePlanReview 
Description
Hillcrest Country Club remodel and addition
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final4/4/20114/5/20114/5/2011APASS
DetailsTom Arcoraci
Aging Inspection4/4/20114/4/20114/4/2011 PASS
DetailsTom Arcoraci
General Inspection1/31/20111/31/20112/2/2011 PASS
DetailsTom Arcoraci
General Inspection11/30/201011/30/201011/30/2010 PASS
DetailsClint A Smith
General Inspection9/29/20109/29/20109/29/2010PPASS
DetailsSteven Webb
Corrections have been made and signage is posted.
BMP Violation8/19/20108/20/20108/20/2010PPART
DetailsClint A Smith
On 8/23/2010 PM, a washout pit will be provided prior to pour of conrete. Will follow-up for compliance with the correction notice. All other issues corrected.
BMP Violation8/19/20108/19/20108/19/2010PCANC
DetailsSteven Webb
Refer to correction notice posted on window of job trailer. Mistake, re-scheduled.
Random Inspection8/19/20108/19/20108/19/2010PFAIL
DetailsSteven Webb
Written correction posted in window at job trailer: Work north side of building, concrete not contained, trackout off site, sign not posted Correct by noon of 8/19 or further enforcement will occur.
General Inspection6/21/20106/21/20106/21/2010 PASS
DetailsSteven Webb
Landscaping in progress, should not be long and the ESC may be finaled.
Random Inspection4/20/20104/20/20104/20/2010PPART
DetailsTom Arcoraci
told rp to clean site
Site Preparation4/20/20104/20/20104/20/2010PCANC
DetailsTom Arcoraci
General Inspection4/2/20104/5/20104/3/2010PCANC
DetailsClint A Smith
General Inspection3/30/20104/2/20104/2/2010ACANC
DetailsClint A Smith
BMP Violation3/26/20103/30/20103/30/2010APART
DetailsClint A Smith
Verbal to RP:
Stay up on general cleanup maintenance. Sweep up hard surface on a daily basis or during the day when sediment and debris on hard surfaces becomes excessive.
General Inspection3/26/20103/26/20103/26/2010PFAIL
DetailsSteven Webb
Issued correction notice, complete all items by the end of the day of 3/29/10; re-inspection will take place on Tuesday 3/30/10 in the a.m..
Random Inspection2/22/20102/22/20102/22/2010APASS
DetailsTom Arcoraci
Random Inspection12/22/200912/22/200912/22/2009APASS
DetailsTom Arcoraci
General Inspection12/10/200912/10/200912/10/2009PPASS
DetailsBob Reichert
looked ok
General Inspection12/1/200912/7/200912/7/2009APASS
DetailsClint A Smith
General Inspection11/30/200912/1/200912/1/2009AFAIL
DetailsClint A Smith
Verbal to RP:
1. Maintain concrete washout prior to next pour date.
2. Protect storm drain inlet within the parking lot to the west.
3. Clean up all hard surfaces of all sediment and debris prior to any storm event and/or 12/04/09 PM. Will re-inspect on 12/7/09am.
Random Inspection11/5/200911/5/200911/6/2009PFAIL
DetailsClint A Smith
Completed yesterday.
Verbal to RP. Clean up all hardsurfaces of all sediment and debris. Will re-inspect on 11/09/09 am
Random Inspection10/29/200911/2/200911/2/2009APASS
DetailsClint A Smith
All issues from the prior inspection have been corrected.
Random Inspection10/22/200910/22/200910/22/2009PPASS
DetailsTom Arcoraci
Random Inspection10/15/200910/15/200910/15/2009PPART
DetailsTom Arcoraci
almost complete
Site Preparation9/28/20099/30/20099/30/2009APART
DetailsClint A Smith
Verbal to RP:
Protect storm drain inlet along Hillcrest to the west of entrance.
Site Preparation9/28/20099/29/20099/28/2009ACANC
DetailsClint A Smith
Moved till 9/30/09 at 9am
Site Preparation9/28/20099/28/20099/28/2009 NR
DetailsClint A Smith
Re-schedule for 9/29/09
Issue & PRINT permit COM  9/21/2009 DONE
Routing - Erosion and Sediment6/26/2009 6/26/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions.
Application received  6/22/2009