Site Final | 12/23/2009 | 12/23/2009 | 12/23/2009 | A | PASS |
Jim Storey
|
|
|
|
General Inspection | 12/22/2009 | 12/22/2009 | 12/22/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok, snow covered
|
General Inspection | 12/21/2009 | 12/21/2009 | 12/21/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
Random Inspection | 12/18/2009 | 12/18/2009 | 12/18/2009 | P | PASS |
Bill VanDegrift
|
|
|
|
Random Inspection | 11/19/2009 | 11/19/2009 | 11/19/2009 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 11/18/2009 | 11/18/2009 | 11/18/2009 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 11/16/2009 | 11/16/2009 | 11/16/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
Random Inspection | 11/9/2009 | 11/9/2009 | 11/9/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
Random Inspection | 11/9/2009 | 11/9/2009 | 11/9/2009 | P | PASS |
Bill VanDegrift
|
|
|
|
Random Inspection | 10/15/2009 | 10/15/2009 | 10/15/2009 | A | PASS |
Jim Storey
|
|
|
|
General Inspection | 9/11/2009 | 9/11/2009 | 9/11/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
Random Inspection | 9/10/2009 | 9/10/2009 | 9/10/2009 | P | PASS |
Eric Strole
|
|
|
|
BMP Violation | 9/9/2009 | 9/10/2009 | 9/10/2009 | A | FAIL |
Eric Strole
|
|
|
stop work till all previous corrections are complete.
|
INSP - Stop Work Order | 9/10/2009 | 9/10/2009 | 9/10/2009 | P | FAIL |
Eric Strole
|
|
|
stop work till all previous corrections are complete.
|
BMP Violation | 9/8/2009 | 9/9/2009 | 9/9/2009 | P | FAIL |
Eric Strole
|
|
|
left verbal & written correction with rp to provide a concrete washout, clean up all concrete that was washed out by street and on site and put in concrete washout & clean up all dirt & debris off all hard surfaces. have complete by days end or a stop work will be issued. will reinspect 9-10-09 am.
|
Random Inspection | 9/8/2009 | 9/8/2009 | 9/9/2009 | P | PART |
Jim Storey
|
|
|
rp voice mail left voice mail to provid wash out pit.
|
Site Preparation | 9/8/2009 | 9/8/2009 | 9/8/2009 | | FAIL |
Eric Strole
|
|
|
left verbal correction with rp via voicemail to post esc sign, provide a concrete washout pit before next pour and slopes over 2 percent grade require sediment barriers. will reinspect 9-9-09 pm.
|
Issue & PRINT permit SFD | | | 9/1/2009 | | DONE |
|
|
|
|
Application received | | | 7/10/2009 | | |
|
|
|
|