Permit Information
Permit NumberESC09-00554
StatusFinaled
Name JERRY WRIGHT
Site Address 618 N ALLUMBAUGH ST
Project NameDarigold
Customer Number 
ePlanReview 
Description
Darigold - Phase II - Shell Addition - //Per Steve Webb ok for Vanauker to pick up permit prior to Bld09-01496 being ready so they can start sitework and temporary loading dock construction. When building permit is issued change to General Contractor's RP if different from orginal and charge transfer fee of $52.50//9/15/09 RMH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection12/17/201012/17/201012/17/2010 DONE
DetailsClint A Smith
DOC - Permit Finaled12/17/201012/17/201012/17/2010PPASS
DetailsClint A Smith
Random Inspection2/19/20102/19/20102/19/2010PPASS
DetailsTom Arcoraci
BMP Violation12/18/200912/22/200912/23/2009APART
DetailsClint A Smith
Verbal to GC:
Scrape and sweep up project area where the staging area is located going out to Allumbaugh street. Will re-inspect on 12/23/09AM.
Tracking Control12/22/200912/23/200912/23/2009APASS
DetailsClint A Smith
BMP Violation12/18/200912/18/200912/18/2009AFAIL
DetailsClint A Smith
Verbal to GC:
Clean up hard surfaces of all sediment and debris. Also in the lay down yard a stabilized construction exit is expected to be constructed. Will re-inspect on 12/22/09AM.
Random Inspection12/4/200912/4/200912/4/2009APASS
DetailsJim Storey
BMP Violation11/20/200911/24/200911/24/2009APASS
DetailsClint A Smith
Random Inspection11/23/200911/23/200911/23/2009APASS
DetailsJim Storey
BMP Violation11/19/200911/20/200911/20/2009PFAIL
DetailsClint A Smith
Verbal to RP:
Back fill silt fence trench.
Make sure when dewatering to be aware where the flow of water is flowing to to keep it going into dense vegitation. Will re-inspect on 11/24/09AM
General Inspection11/19/200911/19/200911/19/2009AFAIL
DetailsClint A Smith
Verbal to GC and RP:
1. Contact city over the RP change.
2. Maintain storm drain at the nirth end of building. Will re-inspect on 11/20/09 PM
Random Inspection11/12/200911/12/200911/12/2009PPASS
DetailsJim Storey
Random Inspection11/10/200911/10/200911/10/2009APASS
DetailsJim Storey
Site Preparation11/5/200911/5/200911/5/2009ACANC
DetailsJim Storey
cloned as noted
Random Inspection11/5/200911/5/200911/5/2009APART
DetailsJim Storey
verbal to have wash out cleaned out or increase the encloser. will be done for insp. next time I am out.
Random Inspection11/4/200911/4/200911/4/2009PPASS
DetailsJim Storey
Random Inspection11/2/200911/2/200911/2/2009PPASS
DetailsJim Storey
Random Inspection10/29/200910/29/200910/29/2009PPASS
DetailsJim Storey
wash out being used and controls all maintaned.
Random Inspection10/28/200910/28/200910/28/2009PPASS
DetailsJim Storey
Random Inspection10/26/200910/26/200910/26/2009PPASS
DetailsJim Storey
Random Inspection10/23/200910/23/200910/23/2009APASS
DetailsJim Storey
Random Inspection10/21/200910/22/200910/22/2009APASS
DetailsJim Storey
Random Inspection10/21/200910/21/200910/21/2009APASS
DetailsJim Storey
Random Inspection10/15/200910/15/200910/15/2009PPART
DetailsJim Storey
verbal as to watching for track out
Random Inspection10/14/200910/14/200910/14/2009PCANC
DetailsJim Storey
Random Inspection10/14/200910/14/200910/14/2009PPASS
DetailsJim Storey
Site Preparation9/22/20099/22/20099/22/2009 PASS
DetailsClint A Smith
Random Inspection9/18/20099/18/20099/18/2009APASS
DetailsJim Storey
PLANS/APPL TAKEN TO FRONT DESK  9/15/2009 DONE
Case Summary (ESC)  9/15/2009  
(F) Reprint permit  9/15/2009 DONE
Permit Ready to Issue  9/15/2009 DONE
Issue & PRINT permit COM  9/15/2009 DONE
Routing - Erosion and Sediment9/11/2009 9/11/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions.
Application received  8/31/2009