General Inspection | 12/23/2011 | 12/23/2011 | 12/23/2011 | | DONE |
Clint A Smith
|
|
|
This area of the harris Ranch master project has been stabilized with hard scape, structures and vegitation.
|
DOC - Permit Finaled | 12/23/2011 | 12/23/2011 | 12/23/2011 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 11/30/2011 | 11/30/2011 | 11/30/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 11/15/2011 | 11/15/2011 | 11/15/2011 | | PART |
Clint A Smith
|
|
|
Area is developed. Waiting on vertical construction on a small portion of lots.
|
General Inspection | 10/28/2011 | 10/28/2011 | 10/31/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/13/2011 | 10/13/2011 | 10/13/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 9/28/2011 | 9/28/2011 | 9/28/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 9/13/2011 | 9/13/2011 | 9/13/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 8/29/2011 | 8/29/2011 | 8/29/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 8/12/2011 | 8/12/2011 | 8/12/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 7/28/2011 | 7/28/2011 | 7/28/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 7/13/2011 | 7/13/2011 | 7/13/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/28/2011 | 6/28/2011 | 6/28/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/13/2011 | 6/13/2011 | 6/13/2011 | | PART |
Clint A Smith
|
|
|
|
General Inspection | 5/27/2011 | 5/27/2011 | 5/27/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/12/2011 | 5/12/2011 | 5/12/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 4/27/2011 | 4/27/2011 | 4/27/2011 | | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Cleanup all tracking within the alley way behind the homes off of Timbersaw. Will re-inspect on 4/28/2011AM.
|
General Inspection | 4/7/2011 | 4/7/2011 | 4/7/2011 | | PART |
Clint A Smith
|
|
|
|
General Inspection | 3/23/2011 | 3/23/2011 | 3/23/2011 | | PART |
Clint A Smith
|
|
|
The stabilized construction enntrance must be extended to the asphalt once work occurs again.
|
BMP Violation | 3/7/2011 | 3/8/2011 | 3/8/2011 | P | PASS |
Clint A Smith
|
|
|
|
Conference | 3/7/2011 | 3/7/2011 | 3/7/2011 | P | DONE |
Steven Webb
|
|
|
Met with Knife River RP C. Bennett and inspector 460. Discussions took place on how to reduce track out, it was agreed to provide access controls and extend the rock entrance as needed where all traffic exiting the project will have to use the rock entrance, (Wise way south of ParkCenter). Inspector 460 will verify the controls are in place.
|
Tracking Control | 3/4/2011 | 3/7/2011 | 3/7/2011 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice Verbal message to RP: 1. Provide access control on the construction exit that is located off of Wise Way. 2. Clean up all tracking in the culdisac off of Warmsprings rd. Failure to comply will result in further enforcement. Will re-inspect on 2/8/2011PM.
|
Tracking Control | 3/4/2011 | 3/4/2011 | 3/4/2011 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Install access control on the access off of Wise Way on the south side of Warmsprings Rd where there is a stabilized construction exit but vechiles are going to the side to access through the project area. Also clean up al sediment off of the hard surfaces within the court on the south side of Warmsprongs Rd. Will re-inspect on 3/7/2011AM.
|
General Inspection | 2/24/2011 | 2/24/2011 | 2/24/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/8/2011 | 2/9/2011 | 2/9/2011 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/8/2011 | 2/8/2011 | 2/8/2011 | | FAIL |
Clint A Smith
|
|
|
Verbal 24hr Correction Notice to RP Listed: Update RP information within a 24hr period or further enforcement will occur. Will re-inspect on 2/9/2011am.
|
General Inspection | 1/21/2011 | 1/21/2011 | 1/21/2011 | | PASS |
Clint A Smith
|
|
|
No activity in the past 30 days.
|
General Inspection | 1/6/2011 | 1/6/2011 | 1/6/2011 | | PART |
Clint A Smith
|
|
|
NO activity due to weather conditions. Once thaw occurs, will discuss with RP over the perventitive measures that need to occur.
|
General Inspection | 12/22/2010 | 12/22/2010 | 12/22/2010 | | PASS |
Clint A Smith
|
|
|
|
General Inspection ESC | 12/1/2010 | 12/1/2010 | 12/1/2010 | | PASS |
Clint A Smith
|
|
|
No activity.
|
BMP Violation | 11/15/2010 | 11/16/2010 | 11/16/2010 | A | PART |
Clint A Smith
|
|
|
After discussing with Knife River we have come to the agreement that they will miniumize tracking off of the project area without installing a stabilized staging area. The area would conflict with there grading operations that is occuring at the moment.
|
BMP Violation | 11/10/2010 | 11/15/2010 | 11/15/2010 | P | CANC |
Clint A Smith
|
|
|
|
Tracking Control | 11/10/2010 | 11/10/2010 | 11/10/2010 | A | FAIL |
Clint A Smith
|
|
|
Notice given to Dave Powell w/ Dallas Harris: 1. Provide a stabilized staging area where, maintianing, staging and fueling can occur on equipment with a stabilized access to minuimize tracking to the maximium extent practible on the north east end of Warm Springs Ave project area. Clean up all tracking that is involve with the project area. **Failure to comply with the given time frame will result in a stop work order.** Will re-inspect on 11/15/2010PM.
|
Tracking Control | 11/1/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Clint A Smith
|
|
|
|
Tracking Control | 10/29/2010 | 11/1/2010 | 11/1/2010 | A | FAIL |
Clint A Smith
|
|
|
Verbal To Curtis Bennet: Install a stabilized construction exit on the south side of warmsprings rd. Will re-inspect on 11/5/2010 AM.
|
Tracking Control | 10/28/2010 | 10/29/2010 | 10/29/2010 | A | CANC |
Clint A Smith
|
|
|
|
General Inspection | 10/18/2010 | 10/18/2010 | 10/18/2010 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection ESC | 10/8/2010 | 10/8/2010 | 10/8/2010 | | PART |
Steven Webb
|
|
|
Verbal to RP, RP needs to verfiy that all denuded soil have been sprayed and then this permit may be transferred to the new another operator, D. Powell which represents Harris Ranch.
|
Conference | 9/21/2010 | 9/23/2010 | 9/23/2010 | A | DONE |
Clint A Smith
|
|
|
Refeer to inspector 420
|
Conference | 9/21/2010 | 9/23/2010 | 9/23/2010 | A | DONE |
Steven Webb
|
|
|
10am: Discussion on compliance to both the Federal CGP and local ESC requirements regarding stabilization and closing out requirements of permit coverage. To summarize, at a minimum, manufactures application rate of soil binder along with perimeter controls (where needed) are expected for compliance. As well, continue to inspect for failure after binders are sprayed. Also discussions on moving from the development phases to vertical construction phase. Expectations for compliance both permit coverage and ESC stormwater and non-stormwater was covered. Developer to continue to visually monitor site discharges during inspections. Met with Knife River, (Jeff) Harris Ranch Engineer, (Dave P.), Knife Rivers repr, (Phil J.) and Boise City ESC inspector (Clint S.).
|
General Inspection | 9/21/2010 | 9/21/2010 | 9/21/2010 | P | DONE |
Clint A Smith
|
|
|
Set up a meeting with Knife RIver and the representative for Dallas Harris for 10am on 9/23/2010.
|
General Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 | A | PART |
Clint A Smith
|
|
|
|
General Inspection ESC | 9/10/2010 | 9/10/2010 | 9/10/2010 | | CANC |
Clint A Smith
|
|
|
|
General Inspection ESC | 8/26/2010 | 8/26/2010 | 8/26/2010 | | PASS |
Clint A Smith
|
|
|
|
General Inspection ESC | 8/11/2010 | 8/11/2010 | 8/11/2010 | | PASS |
Clint A Smith
|
|
|
|
General Inspection ESC | 7/26/2010 | 7/26/2010 | 7/27/2010 | | PART |
Clint A Smith
|
|
|
Project is ulitilizing there storm water ponds that all of the storm drain system feeds into as there Passive Treatment System. Ponds at the time are self contained and do not enter the Water of the US due to a plug at the inlet of the poutlet pipe.
|
General Inspection ESC | 7/27/2010 | 7/27/2010 | 7/27/2010 | | CANC |
Steven Webb
|
|
|
Duplicate
|
General Inspection ESC | 7/9/2010 | 7/9/2010 | 7/9/2010 | | PART |
Clint A Smith
|
|
|
Need to stay up on sweeping up at all accesses of the project area from the subbase to the paved streets.
|
General Inspection | 6/16/2010 | 6/24/2010 | 6/24/2010 | A | DONE |
Clint A Smith
|
|
|
They have removed the construction exit due to the phase of the road base for the road construction.
|
Tracking Control | 6/21/2010 | 6/21/2010 | 6/21/2010 | P | PART |
Steven Webb
|
|
|
Verbal correction to K. Baty, RP, Top dressing of rock has been installed on the ParkCenter entrance but rock entrance south of Barber is in need of rock.
|
General Inspection | 6/16/2010 | 6/16/2010 | 6/16/2010 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Maintain dust by using the given dust control measures illistrated with the approved ESC plan.
|
General Inspection ESC | 6/16/2010 | 6/16/2010 | 6/16/2010 | | PART |
Steven Webb
|
|
|
Verbal to RP: Construction entrances (2) needs to be maintained including correct types of material and the one off of Barber needs widened. Discussed final stabilization. Around ponds topsoil is in place and other misc. areas topsoil is being placed. Power service to site is needed to run irrigation, this issue is being worked. As soon as power is in place then seeding can be done and watering will cause growth. Old sediment barriers are expected to be removed if no longer needed.
|
Complaint Inspection | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PART |
Steven Webb
|
|
|
DEQ M. Van K. water and stockpile soils needs to be sampled, water under method 8260 and soils TPH. Do not proceed with work in this area until the sample results indicate under standards.
|
General Inspection ESC | 5/28/2010 | 5/28/2010 | 5/28/2010 | | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 4/22/2010 | 4/26/2010 | 4/26/2010 | A | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 4/22/2010 | 4/22/2010 | 4/22/2010 | P | FAIL |
Clint A Smith
|
|
|
Correction Notice: 1. Add additional material or High visability construction fence with T-post an both end of the new Barber Rd. 2. Install the rolled erosion control blanket within the storm water channel in the whole channel per the manufactures specifications. Also provide the city with the specifiactions to verify. 3. Provide the proper info regarding the RP on the ESC sign. * Failure to comply will result in a stop work order. Will re-inspect on 4/26/10AM.
|
Tracking Control | 4/15/2010 | 4/19/2010 | 4/19/2010 | A | PART |
Clint A Smith
|
|
|
Verbal to RP: Once the tie ends are complete at the north end of project, If they area going to be accessing that area a stabilized construction exit is required.
|
Tracking Control | 4/15/2010 | 4/15/2010 | 4/15/2010 | P | FAIL |
Clint A Smith
|
|
|
Correction Notice: 1. Install a stabilized construction exit per industry standards at both access points on the new Barber Rd. Or Block off using T-post and high visability construction fence. 2. Maintain both construction exits onto Warm Springs Rd. ** Failure to comply will result in further enforcement. Will re-inspect on 4/19/10AM.
|
General Inspection | 4/7/2010 | 4/13/2010 | 4/13/2010 | A | PART |
Clint A Smith
|
|
|
They will be using a seed, tach, mulch application on the slopes of the channel. Also requiring an approved blanket over the top of the application to hold the seed on the banks.
|
Tracking Control | 4/7/2010 | 4/7/2010 | 4/7/2010 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: No later than 4/13/10 we must see that at the north end of project area either block off access and or install a stabilized construction exit. Keep up with sweeping. Also told RP to figure out how they will be stabilizing the channel that connects the three ponds. We also cannot have a active water flow in the channel until the time of achieving final stabilization with in the whole channel. Will follow up on 4/13/10AM.
|
General Inspection | 3/23/2010 | 3/23/2010 | 3/23/2010 | A | PART |
Clint A Smith
|
|
|
Verbal to RP: Clean up tracking at the north east end of project. A stabilized access will be installed by next week after utilites are installed.
|
Site Preparation | 3/19/2010 | 3/19/2010 | 3/19/2010 | P | PASS |
Clint A Smith
|
|
|
Dewatering from the third pond has been completed as of 3/18/10.
|
General Inspection | 3/17/2010 | 3/17/2010 | 3/17/2010 | P | PART |
Clint A Smith
|
|
|
Walk area with Gary w/ Knife River and spoke to the RP over the concerns of water level in both exsisting ponds. Told them to keep an eye on the levels. Alos told RP to utilize access controls along the Barber Rd. area where they have removed the road to pervent tracking off onto Warmsprings rd.
|
General Inspection | 3/11/2010 | 3/12/2010 | 3/12/2010 | A | PART |
Clint A Smith
|
|
|
All water is beiing container on the Harris Ranch land. Left a Message for the RP over access control on and offo f the site where tracking has occured. Will re-inspect on 3/15/10AM
|
General Inspection | 3/11/2010 | 3/11/2010 | 3/11/2010 | P | DONE |
Clint A Smith
|
|
|
Refer to #420 note. Will be inspecting on a daily basis until the dewatering is complete.
|
BMP Violation | 3/10/2010 | 3/11/2010 | 3/11/2010 | P | PART |
Steven Webb
|
|
|
Inspect de-watering activities: Inspected the site for compliance, problems relating to de-watering is being worked by Knife River (Gary T. ###-####). Work is being performed to divert water east of Wellings Creek. At site inspection the water is retained into the Cattle Field. Ditch running through the field has direct discharge into the Boise River, but no water has reached the river. Reviewed the holding are south of the fence at the ditch and recommended to Gary T. to install checks and rock berm to allow for possible flows to be retained. Boise City will be inspecting on a daily basis until de-watering is completed. Verbal to Knife River to install a satisfactory rock construction exit at Warm Springs Ave. Inspector 460 will re-inspect on 3/12.
|
Complaint Inspection | 3/10/2010 | 3/10/2010 | 3/10/2010 | P | PART |
Steven Webb
|
|
|
Received call from ACHD, Inspector 460 visited site and provide a report to ESC Inspector 420. Called applicant, consultent and Eng. Reminder all parties of the conditions of the permit. Discharges not to exceed pre-development flows into Wallings Creek. Informed parties to manage de-watering according to local and Federal regulations. Inspection will occur on Thursday 3-11 afternoon and if problems persist then a stop work on de-watering will be issued.
|
General Inspection | 2/25/2010 | 3/3/2010 | 3/3/2010 | A | CANC |
Clint A Smith
|
|
|
|
Random Inspection | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | PASS |
Clint A Smith
|
|
|
Work is only occuring on the south side of Warmsprings road. Are activily dewatering from multiple location on the project into the 2nd sediment basin. No issues found on or off site at this time. Will re-inspect on 3/3/10am.
|
Site Preparation | 2/22/2010 | 2/22/2010 | 2/22/2010 | A | DONE |
Clint A Smith
|
|
|
No activity.
|
General Inspection | 2/2/2010 | 2/9/2010 | 2/9/2010 | A | PART |
Clint A Smith
|
|
|
Verbal to RP: Need to flare out the rock to cover the are coming into the project area to the south east of access.
|
General Inspection | 2/4/2010 | 2/4/2010 | 2/4/2010 | P | PART |
Steven Webb
|
|
|
Verbal to RP, Randy, need to maintain construction entrance. Complete within two working days. No other activity observed.
|
General Inspection | 1/26/2010 | 2/2/2010 | 2/2/2010 | A | PART |
Clint A Smith
|
|
|
Verbal to RP: Prior to th start of activity, need to maintain construction exit an add additional exit where needed to miniumize thack out. Will follow up in the near future.
|
Site Preparation | 1/22/2010 | 1/26/2010 | 1/26/2010 | A | PASS |
Clint A Smith
|
|
|
Dewatering at the North west end of project into the pond. NO issues present.
|
Site Preparation | 1/22/2010 | 1/22/2010 | 1/22/2010 | | PART |
Clint A Smith
|
|
|
Starting to mobilize equiptment. But due to the weather no activity is occuring. Will re-inspect on 1/26/10 am.
|
Conference | 1/15/2010 | 1/15/2010 | 1/15/2010 | P | DONE |
Steven Webb
|
|
|
1:30 Pre-Construction Meeting: Met with Harris Ranch Rep, D. Powell, Contractor, Jeff & Randy and 3rd party consultant, P. Jones. Reviewed ESC including permit conditions, stabilization requirements, dewatering (only pre-development flow rates are allowed into Walling Creek) and water must meet water quality standards, transfering permits to another party and the upcoming Jan. 29th ESC workshop.
|
Conference | 1/15/2010 | 1/15/2010 | 1/15/2010 | P | DONE |
Clint A Smith
|
|
|
refer to #420 notes.
|
Issue & PRINT permit COM | | | 1/15/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2010 | | DONE |
|
|
|
|
Telephone call | | | 1/13/2010 | | DONE |
|
|
|
called Randy permit ready and fee given 1-13-10 dld
|
Routing - Erosion and Sediment | 1/8/2010 | | 1/12/2010 | | PASS |
Steven Webb
|
|
|
|
Routing - Erosion and Sediment | 1/11/2010 | | 1/12/2010 | | PASS |
Steven Webb
|
|
|
ESC plan approved along with the permit conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2010 | | |
|
|
|
|
Application received | | | 1/8/2010 | | |
|
|
|
|