Site Final | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PASS |
Mike Jordan
|
|
|
Final stabalization is now completed.
|
Site Final | 4/22/2010 | 4/22/2010 | 4/22/2010 | P | FAIL |
Mike Jordan
|
|
|
Final stabalization not completed.
|
Random Inspection | 3/17/2010 | 3/17/2010 | 3/17/2010 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 3/16/2010 | 3/16/2010 | 3/16/2010 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
General Inspection | 3/15/2010 | 3/15/2010 | 3/15/2010 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
General Inspection | 3/15/2010 | 3/15/2010 | 3/15/2010 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 3/8/2010 | 3/9/2010 | 3/9/2010 | A | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 2/17/2010 | 2/18/2010 | 2/18/2010 | P | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 2/17/2010 | 2/17/2010 | 2/17/2010 | | FAIL |
Clint A Smith
|
|
|
Verbal message to RP: 1. Clean up all hard surface of all sediment and debris. 2. Place all concrete washot into the washout pit. Will re-inspect on 2/18/10 PM.
|
Random Inspection | 2/16/2010 | 2/16/2010 | 2/16/2010 | P | PASS |
Mike Jordan
|
|
|
|
Site Preparation | 2/12/2010 | 2/12/2010 | 2/12/2010 | A | PASS |
Mike Jordan
|
|
|
ESC permit sign is posted. BMP;s and washout in place.
|
Issue & PRINT permit SFD | | | 2/10/2010 | | DONE |
|
|
|
|
Application received | | | 1/25/2010 | | |
|
|
|
|