Site Final | 8/17/2010 | 8/17/2010 | 8/17/2010 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 8/17/2010 | 8/17/2010 | 8/17/2010 | P | PASS |
Mike Jordan
|
|
|
Final stabalization completed.
|
Random Inspection | 7/23/2010 | 7/23/2010 | 7/23/2010 | P | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 7/7/2010 | 7/7/2010 | 7/7/2010 | A | PASS |
Mike Jordan
|
|
|
|
Site Final | 6/11/2010 | 6/11/2010 | 6/11/2010 | P | CANC |
Mike Jordan
|
|
|
|
BMP Violation | 6/9/2010 | 6/9/2010 | 6/9/2010 | P | PASS |
Mike Jordan
|
|
|
Landscapping work has been in progress. Almost complete. Noted daily cleaning and sweeping of all hardsurfaces. Site condotions at this time are good.
|
Random Inspection | 5/25/2010 | 5/25/2010 | 5/25/2010 | A | PART |
Mike Jordan
|
|
|
ESC permit sign posted. BMP's in place. General site conditions ok. Needs to sweep silts off of hard surfaces. Verbal to RP.
|
BMP Violation | 4/16/2010 | 4/16/2010 | 4/16/2010 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | PART |
Mike Jordan
|
|
|
Needs to perform some general cleanup of jobsite and sweepsidewalks and gutterpan of silts and debrie.
|
BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 | P | PART |
Mike Jordan
|
|
|
Work in progress on cleanup.
|
Random Inspection | 4/5/2010 | 4/5/2010 | 4/5/2010 | A | PASS |
Mike Jordan
|
|
|
|
Tracking Control | 3/26/2010 | 3/26/2010 | 3/26/2010 | A | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 3/24/2010 | 3/24/2010 | 3/24/2010 | P | PASS |
Mike Jordan
|
|
|
|
Tracking Control | 3/19/2010 | 3/19/2010 | 3/19/2010 | P | PASS |
Mike Jordan
|
|
|
|
Tracking Control | 3/15/2010 | 3/17/2010 | 3/17/2010 | A | PASS |
Clint A Smith
|
|
|
|
Tracking Control | 3/15/2010 | 3/15/2010 | 3/15/2010 | P | FAIL |
Clint A Smith
|
|
|
Clean up all sediment and debris off of all hardsurfaces. Clean up all tracking also. Will re-inspect on 3/17/10AM.
|
Tracking Control | 3/11/2010 | 3/11/2010 | 3/11/2010 | A | PART |
Mike Jordan
|
|
|
Noted some trackout. RP was notified.
|
BMP Violation | 3/8/2010 | 3/8/2010 | 3/8/2010 | P | PART |
Mike Jordan
|
|
|
BAckfill operations in progress. Sediment controls in place. Will need to sweep at end of day. No trackout at this time.
|
Site Preparation | 3/4/2010 | 3/4/2010 | 3/5/2010 | | CANC |
Steven Webb
|
|
|
already done
|
Site Preparation | 3/4/2010 | 3/4/2010 | 3/4/2010 | | PART |
Steven Webb
|
|
|
washout maintenance, barriers, protect d.i.
|
Random Inspection | 3/2/2010 | 3/2/2010 | 3/2/2010 | P | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 3/1/2010 | 3/1/2010 | 3/1/2010 | P | PASS |
Mike Jordan
|
|
|
|
Site Preparation | 2/25/2010 | 2/26/2010 | 3/1/2010 | P | PASS |
Mike Jordan
|
|
|
|
Site Preparation | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | CANC |
Mike Jordan
|
|
|
|
Issue & PRINT permit SFD | | | 2/25/2010 | | DONE |
|
|
|
|
Application received | | | 2/1/2010 | | |
|
|
|
|