Site Preparation | 1/5/2011 | 1/5/2011 | 1/5/2011 | P | CANC |
Clint A Smith
|
|
|
Wrong permit
|
Site Final | 8/23/2010 | 8/23/2010 | 8/23/2010 | P | DONE |
Steven Webb
|
|
|
Site stabilized
|
DOC - Permit Finaled | 8/23/2010 | 8/23/2010 | 8/23/2010 | P | PASS |
Steven Webb
|
|
|
|
Random Inspection | 8/10/2010 | 8/10/2010 | 8/10/2010 | A | PART |
Bill VanDegrift
|
|
|
looks ok just needs to sweep
|
BMP Violation | 7/8/2010 | 7/9/2010 | 7/9/2010 | A | DONE |
Clint A Smith
|
|
|
went over with the issue of what occured with the dewatering and told them options of how they could have achieved compliance.
|
Random Inspection | 7/8/2010 | 7/8/2010 | 7/9/2010 | P | FAIL |
Clint A Smith
|
|
|
Stopped the dewatwering operation into the valley gutter and recommended the RP to utilize a Sediment bag into the grassy area to the west of the project area. Will follow up tomorrow for clean up after the work is comppleted.
|
Random Inspection | 7/8/2010 | 7/8/2010 | 7/8/2010 | P | PART |
Bill VanDegrift
|
|
|
talked to rp about dewatering sewer connection ditch.
|
Random Inspection | 7/6/2010 | 7/6/2010 | 7/6/2010 | P | PASS |
Jim Storey
|
|
|
|
Random Inspection | 6/25/2010 | 6/25/2010 | 6/25/2010 | P | PASS |
Jim Storey
|
|
|
|
General Inspection | 6/15/2010 | 6/15/2010 | 6/15/2010 | P | PASS |
Steven Webb
|
|
|
Dewatering terminated: Backfilling being performed.
|
Random Inspection | 6/8/2010 | 6/8/2010 | 6/8/2010 | P | PASS |
Jim Storey
|
|
|
|
Complaint Inspection | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Steven Webb
|
|
|
Walgreens parking lot contained no standing water. Water is being channeled along the curb to the nearest drop inlet. Water is clear. Contractor estimated another two weeks of de-watering.
|
Random Inspection | 5/26/2010 | 5/26/2010 | 5/26/2010 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 5/18/2010 | 5/18/2010 | 5/18/2010 | P | PASS |
Jim Storey
|
|
|
|
Random Inspection | 5/13/2010 | 5/13/2010 | 5/13/2010 | P | PART |
Steven Webb
|
|
|
Observed turbid discharge coming from the project. Informed RP that they need to address this discharge, they unhooled and ran the line into a water truck which would then return to the plant to discharge. Minor discharge due to compaction caused vibrations enough to cause fine material to enter the well point. Site is at the final elevation, de-watering will continue until the bottom & 1st floors and walls are poured and backfilled, if not the structure could "float" due to the water pressure.
|
Site Preparation | 5/4/2010 | 5/7/2010 | 5/7/2010 | A | PASS |
Steven Webb
|
|
|
Sign is posted, de-watering is occurring and discharge is clear. Reviewed concrete washout procedures with contractor.
|
BMP Violation | 5/5/2010 | 5/6/2010 | 5/6/2010 | P | PASS |
Troy James
|
|
|
reinspect site prep site prep ok, dewatering system working good
|
General Inspection | 5/6/2010 | 5/6/2010 | 5/6/2010 | A | PASS |
Clint A Smith
|
|
|
Dewatering is occuring from the well. No excavating has occured eyt. Wil re-inspect on 5/7/10am.
|
Conference | 5/4/2010 | 5/5/2010 | 5/5/2010 | A | DONE |
Steven Webb
|
|
|
10:00 on site: Met with contractor, RP, ACHD, Inspector 460 and 435. Reviewed de-watering procedures, including continuous dewatering. Ok to discharge into the storm drain drop inlet as long as the water is not turbid beyond standards. As well, reviewed trackout, debris, sign, etc. requirements. We will be following up.
|
Conference | 5/4/2010 | 5/5/2010 | 5/5/2010 | A | DONE |
Clint A Smith
|
|
|
Refer inspector 420
|
Conference | 5/4/2010 | 5/5/2010 | 5/5/2010 | A | DONE |
Troy James
|
|
|
10:00 on site
|
Site Preparation | 5/4/2010 | 5/4/2010 | 5/5/2010 | | FAIL |
Troy James
|
|
|
met with clint, steve and dan the rp on site to discuss dewatering and proper bmp's placement, rp needs to remove wattles or install them correctly for now, need to add more rock for tracking at curving to asphalt and post sign
|
Issue & PRINT permit COM | | | 4/27/2010 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/5/2010 | | 4/5/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the permit's conditions.
|
Application received | | | 3/8/2010 | | |
|
|
|
|