General Inspection | 12/23/2010 | 12/23/2010 | 12/23/2010 | | DONE |
Clint A Smith
|
|
|
Permit finalled.
|
DOC - Permit Finaled | 12/23/2010 | 12/23/2010 | 12/23/2010 | P | PASS |
Clint A Smith
|
|
|
|
Random Inspection | 6/9/2010 | 6/9/2010 | 6/9/2010 | P | PASS |
Mike Jordan
|
|
|
ESC permit sign posted. BMP's in place. Majority of demolition and all slab saw cutting is now completed. Site was clean and orderly.
|
Random Inspection | 5/13/2010 | 5/13/2010 | 5/14/2010 | P | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 5/11/2010 | 5/11/2010 | 5/11/2010 | A | PASS |
Mike Jordan
|
|
|
|
Override - Parcel Holds | | | 5/11/2010 | | |
|
|
|
|
General Inspection | 5/4/2010 | 5/5/2010 | 5/7/2010 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/3/2010 | 5/4/2010 | 5/4/2010 | A | CANC |
Clint A Smith
|
|
|
Moved to 5/5/10am.
|
General Inspection | 4/22/2010 | 5/3/2010 | 5/3/2010 | A | CANC |
Clint A Smith
|
|
|
|
Site Preparation | 4/21/2010 | 4/22/2010 | 4/22/2010 | A | PART |
Clint A Smith
|
|
|
Prior to the footing pour date, must provide an external washout. Will be contqacted by the RP to verify the implementation of the washout. Will re-inspect on 5/3/10am
|
Site Preparation | 4/22/2010 | 4/22/2010 | 4/22/2010 | A | PART |
Mike Jordan
|
|
|
ESC permit sign posted. Needs to provide di protection. Verbal c/n to RP.
|
Site Preparation | 4/21/2010 | 4/21/2010 | 4/21/2010 | | NR |
Clint A Smith
|
|
|
Will be inspecting at 10am to meet with RP.
|
Issue & PRINT permit COM | | | 4/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 4/8/2010 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Erosion and Sediment | 4/7/2010 | | 4/7/2010 | | DONE |
Tim L. Woodard
|
|
|
**Waiver Approved - applicant to comply with all attached conditions. TLW**
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 3/12/2010 | | DONE |
Tisha Gallop
|
|
|
|