General Inspection | 2/9/2011 | 2/9/2011 | 2/9/2011 | | DONE |
Clint A Smith
|
|
|
Permit Finalled.
|
Site Final | 2/9/2011 | 2/9/2011 | 2/9/2011 | P | PASS |
Clint A Smith
|
|
|
|
Complaint Inspection | 1/25/2011 | 1/25/2011 | 1/25/2011 | A | PART |
Steven Webb
|
|
|
send complaint insp to 420 per Clint S. Talked to RP and he said they would correct the old construction fencing . Informed complaintee of status and gave him the contractors name and telephone number. As well, gave complaintee my phone number and requested he call me for further discussions.
|
Change Status (ISS) | | | 1/25/2011 | | DONE |
Tisha Gallop
|
|
|
reopen per 460, project not completed
|
General Inspection ESC | 5/28/2010 | 5/28/2010 | 6/1/2010 | | DONE |
Clint A Smith
|
|
|
|
DOC - Permit Finaled | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 3/29/2010 | 4/9/2010 | 4/9/2010 | A | PASS |
Steven Webb
|
|
|
Staging area for Ada County river stabilziation project. Trout Unlimited.
|
Site Preparation | 3/29/2010 | 3/29/2010 | 3/29/2010 | | NR |
Steven Webb
|
|
|
Trout Unlimited have not started project. Discussed staging area with Andy and summarized details to reduce tracking onto greenbelt. Andy will provide schedule information to ESC prior to start of work.
|
Issue & PRINT permit COM | | | 3/22/2010 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/16/2010 | | 3/17/2010 | | PASS |
Steven Webb
|
|
|
ESC plan waiver is approved according to the ESC permit's attached conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2010 | | |
|
|
|
|
Permit Ready to Issue | | | 3/17/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/17/2010 | | DONE |
Barbara Stitt
|
|
|
Called Andy Brunelle and told him permit is ready and fees due///3-17-10 @ 3:15pm BAS
|
Application received | | | 3/16/2010 | | DONE |
Tisha Gallop
|
|
|
|