General Inspection | 12/12/2011 | 12/12/2011 | 12/19/2011 | | DONE |
Clint A Smith
|
|
|
Permit finaled.
|
DOC - Permit Finaled | 12/19/2011 | 12/19/2011 | 12/19/2011 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/10/2011 | 10/10/2011 | 10/10/2011 | | CANC |
Alan Hauser
|
|
|
|
General Inspection | 8/8/2011 | 8/8/2011 | 8/9/2011 | | PASS |
Jim Johnson
|
|
|
|
General Inspection | 6/6/2011 | 6/6/2011 | 6/8/2011 | | CANC |
Jim Johnson
|
|
|
|
General Inspection | 4/4/2011 | 4/4/2011 | 4/6/2011 | | PART |
Jim Johnson
|
|
|
talked to general contractor on site still working on stabilization of disturded area of project
|
Conference | 2/1/2011 | 2/1/2011 | 2/1/2011 | P | CANC |
Clint A Smith
|
|
|
could not reach RP via phone and was noyt on site.
|
Site Final | 1/31/2011 | 1/31/2011 | 1/31/2011 | A | NR |
Tom Arcoraci
|
|
|
|
BMP Violation | 12/15/2010 | 12/17/2010 | 12/17/2010 | A | PASS |
Clint A Smith
|
|
|
|
Tracking Control | 12/15/2010 | 12/15/2010 | 12/15/2010 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Cleanup all hard surfaces within the project area. Must be comppleted by the end of day 0n 12/16/2010. Will re-inspect on 12/17/2010AM. Photo's taken of the project conditions prior to clean up.
|
BMP Violation | 12/1/2010 | 12/2/2010 | 12/2/2010 | A | PART |
Clint A Smith
|
|
|
|
BMP Violation | 11/30/2010 | 12/1/2010 | 12/1/2010 | P | PART |
Clint A Smith
|
|
|
HAve begun o correct the violaion that were posted. Will re-inspect for full complaine on 12/2/10am.
|
BMP Violation | 11/30/2010 | 11/30/2010 | 11/30/2010 | P | FAIL |
Clint A Smith
|
|
|
CORRECTION NOTICE: 1. Clean up all sediment and debris off of all hard surfaces. 2. Due to weather conditions doulbe protectthe storm drains with an external protection of a weighted wattle. 3. Update Responsible person info with the city. 4. Install a weighted sediment barrier behind both asphalt cuts to the disturbed soil. Failure to comply wwill result in a stop work order. Will re-inspect on 12/1/2010PM.
|
Site Preparation | 11/3/2010 | 11/4/2010 | 11/4/2010 | A | PASS |
Jim Sly
|
|
|
Zach phone...............They have Conc wash out pit with sign......protection at stockpile dirt.
|
Site Preparation | 11/1/2010 | 11/2/2010 | 11/2/2010 | A | PART |
Jim Sly
|
|
|
Zach phone Need Concrete washout pit and sign for it prior to pouring.....they said they would dig one.......Need to protect, contain or remove stockpiled dirt located on hard surfaces.
|
Site Preparation | 10/19/2010 | 10/19/2010 | 10/19/2010 | | PASS |
Clint A Smith
|
|
|
|
Issue & PRINT permit COM | | | 10/12/2010 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/12/2010 | | 5/12/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the plan and ESC permit conditions.
|
Application received | | | 4/30/2010 | | |
|
|
|
|