Site Final | 11/4/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 11/1/2010 | 11/2/2010 | 11/2/2010 | A | PART |
Jim Storey
|
|
|
|
Site Final | 8/5/2010 | 8/5/2010 | 8/5/2010 | P | FAIL |
Mike Jordan
|
|
|
Does not appear that final stabalization has been completed.
|
Random Inspection | 6/29/2010 | 6/29/2010 | 6/29/2010 | P | PASS |
Troy James
|
|
|
|
General Inspection | 6/28/2010 | 6/28/2010 | 6/28/2010 | P | PART |
Steven Webb
|
|
|
Verbal to RP, clean hard surfaces of sediment and the curb of concrete dried residual.
|
Random Inspection | 6/14/2010 | 6/14/2010 | 6/14/2010 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 6/9/2010 | 6/9/2010 | 6/9/2010 | P | PART |
Jim Storey
|
|
|
sign in place signed off for other componants by 420
|
Site Preparation | 6/7/2010 | 6/7/2010 | 6/7/2010 | P | PART |
Steven Webb
|
|
|
Verbal to RP: Sign needs to be posted and clean up of dirt from sidewalk, gutter, etc. by the end of the day. Sediment barriers are in place downslope.
|
Issue & PRINT permit SFD | | | 5/12/2010 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/3/2010 | | 5/3/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and permit's conditions.
|
Application received | | | 4/30/2010 | | |
|
|
|
|