General Inspection | 4/27/2011 | 4/27/2011 | 4/27/2011 | | DONE |
Steven Webb
|
|
|
|
DOC - Permit Finaled | 4/27/2011 | 4/27/2011 | 4/27/2011 | P | PASS |
Steven Webb
|
|
|
|
General Inspection | 2/23/2011 | 2/23/2011 | 2/23/2011 | | PASS |
Clint A Smith
|
|
|
Minor work is still occuring but all denuded soil is stabilized.
|
General Inspection | 12/24/2010 | 12/24/2010 | 12/27/2010 | | CANC |
Steven Webb
|
|
|
Holiday
|
BMP Violation | 9/22/2010 | 9/22/2010 | 9/22/2010 | A | PASS |
Mike Jordan
|
|
|
|
BMP Violation | 9/8/2010 | 9/8/2010 | 9/8/2010 | A | PART |
Clint A Smith
|
|
|
Initiated sweeping of hard surfaces. And prior to any storm events will be covering any stockpiles on site that could effect storm drain system.
|
General Inspection | 9/3/2010 | 9/3/2010 | 9/3/2010 | A | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 8/12/2010 | 8/12/2010 | 8/12/2010 | A | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 7/27/2010 | 7/27/2010 | 7/27/2010 | A | PASS |
Jim Storey
|
|
|
|
Site Preparation | 7/22/2010 | 7/22/2010 | 7/22/2010 | P | PASS |
Mike Jordan
|
|
|
Concrete washout has been placed.
|
Site Preparation | 7/21/2010 | 7/21/2010 | 7/21/2010 | | PART |
Clint A Smith
|
|
|
Providing a washout for the footing pours.
|
Site Preparation | 7/21/2010 | 7/21/2010 | 7/21/2010 | | CANC |
Steven Webb
|
|
|
duplication
|
Site Preparation | 7/15/2010 | 7/15/2010 | 7/15/2010 | A | PASS |
Clint A Smith
|
|
|
Stop work order has been lifted from the project. Permit has been issued and all bmp's during this phase are installed.
|
Issue & PRINT permit COM | | | 7/14/2010 | | DONE |
|
|
|
|
INSP - Stop Work Order | 7/12/2010 | 7/12/2010 | 7/12/2010 | P | FAIL |
Clint A Smith
|
|
|
Stop Work Order issued: Working without aquiring a valid permit. Permit is still in reveiw phase. Double fee on the Erosion control Permit. Instructed Matt with Kriezenbeck (GC) over the details of the stop work order. No activity can occur if not erosion and sediment control activities. Once the permit has been issued, a site preperation inspection must be scheduled and a pass must be achieved to have the stop work order removed. Will re-inspect once a site preperation isnpection is scheduled.
|
Routing - Erosion and Sediment | 5/18/2010 | | 5/18/2010 | | PASS |
Clint A Smith
|
|
|
ESC plan approved with attached conditions.
|
Application received | | | 5/6/2010 | | |
|
|
|
|