Aging Inspection | 5/11/2011 | 5/11/2011 | 5/11/2011 | | DONE |
Clint A Smith
|
|
|
Permit finaled.
|
DOC - Permit Finaled | 5/11/2011 | 5/11/2011 | 5/11/2011 | P | PASS |
Clint A Smith
|
|
|
|
Site Final | 12/15/2010 | 12/15/2010 | 12/15/2010 | A | FAIL |
Mike Jordan
|
|
|
Final stabalization not completed.
|
Random Inspection | 9/13/2010 | 9/13/2010 | 9/13/2010 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 9/3/2010 | 9/3/2010 | 9/3/2010 | P | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 8/17/2010 | 8/17/2010 | 8/17/2010 | A | PASS |
Bill VanDegrift
|
|
|
looks good
|
Random Inspection | 8/12/2010 | 8/12/2010 | 8/12/2010 | A | PASS |
Bill VanDegrift
|
|
|
looks ok
|
Random Inspection | 7/12/2010 | 7/12/2010 | 7/12/2010 | P | PASS |
Mike Jordan
|
|
|
|
Site Preparation | 6/30/2010 | 6/30/2010 | 6/30/2010 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved.
|
Site Preparation | 6/29/2010 | 6/29/2010 | 6/29/2010 | | CANC |
Clint A Smith
|
|
|
Completed by inspector 450
|
Conference | 6/29/2010 | 6/29/2010 | 6/29/2010 | P | DONE |
Steven Webb
|
|
|
Building received correction from inspector 450 and informed contractor that concrete cannot be placed due to the fact of having no washout containment area. SGW informed builder that concrete can be placed if a proper washout area is provided. All other correction items to be completed by next inspection for the foundation wall. Informed inspector 450 of the discussion and summary of the conversation with the contractor. Compliance is expected.
|
Site Preparation | 6/29/2010 | 6/29/2010 | 6/29/2010 | P | FAIL |
Mike Jordan
|
|
|
ESC permit sign posted. No concrete washout. Also needs to install silt fence around perimeter against chain link fence. Verbal correction notice given to RP. No concrete will be allowed at this tome.
|
Issue & PRINT permit SFD | | | 6/22/2010 | | DONE |
|
|
|
|
Application received | | | 5/25/2010 | | |
|
|
|
|