Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberESC10-00473
StatusFinaled
Name TONY O'NEIL
Site Address 8233 W FRANKLIN RD
Project NameCafe Rio
Customer Number 
ePlanReview 
Description
under slab plumbing and excavation to connect to utilities and new grease interceptor.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final9/10/20109/10/20109/10/2010APASS
DetailsClint A Smith
General Inspection9/7/20109/7/20109/7/2010APASS
DetailsMike Jordan
Random Inspection8/25/20108/25/20108/25/2010PPASS
DetailsMike Jordan
General Inspection8/18/20108/18/20108/18/2010APASS
DetailsMike Jordan
Random Inspection8/13/20108/13/20108/13/2010APASS
DetailsMike Jordan
General Inspection8/12/20108/12/20108/12/2010PPASS
DetailsMike Jordan
Random Inspection8/10/20108/10/20108/10/2010APASS
DetailsMike Jordan
Random Inspection8/9/20108/9/20108/9/2010APASS
DetailsMike Jordan
Random Inspection8/6/20108/6/20108/6/2010APASS
DetailsMike Jordan
Random Inspection8/5/20108/5/20108/5/2010PPASS
DetailsMike Jordan
Random Inspection8/5/20108/5/20108/5/2010APASS
DetailsMike Jordan
Site Preparation8/4/20108/4/20108/4/2010 PART
DetailsClint A Smith
Verbal to RP:
Must provide a washout for the project. RP will make sure that it will inplace prior to any washing of any non stormwater pollutants.
BMP Violation8/4/20108/4/20108/4/2010PPASS
DetailsMike Jordan
Washout has been established, di protection installed as well as sediment barriers for all on site stock material.
Site Preparation7/30/20107/30/20107/30/2010PPART
DetailsJim Sly
Tony phone Need concrete washout pit or receptical prior to pouring concrete.
Issue & PRINT permit COM  7/28/2010 DONE
BMP Violation7/14/20107/16/20107/16/2010APART
DetailsClint A Smith
Must provide a washout prior to any non storm water pollutants can be washed out and contained.
BMP Violation7/14/20107/14/20107/14/2010PCANC
DetailsClint A Smith
wrong date
BMP Violation7/14/20107/16/20107/14/2010ACANC
DetailsClint A Smith
Site Preparation7/14/20107/14/20107/14/2010 FAIL
DetailsClint A Smith
Verbal to RP:
1. Provide a non storm water pollutant washout.
2. Provide a storm drain inlet protection at the storm drain at the west end of the project.
3. Post ESC sign at the front of the building.
Will re-inspect on 7/16/10am.
Issue & PRINT permit COM  7/7/2010 DONE
Routing - Erosion and Sediment6/14/2010 6/14/2010 PASS
DetailsSteven Webb
ESC plan waiver is approved according to the ESC permit attached conditions. Certified RP is required prior to issuance of permits.
Application received  6/8/2010