General Inspection | 5/20/2011 | 5/20/2011 | 5/20/2011 | | DONE |
Clint A Smith
|
|
|
PErmit finaled..
|
DOC - Permit Finaled | 5/20/2011 | 5/20/2011 | 5/20/2011 | P | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 3/30/2011 | 4/4/2011 | 4/4/2011 | A | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 3/28/2011 | 3/30/2011 | 3/30/2011 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice still stands. Date of completion has been extend to 4/1/2011PM. Will re-inspect on 4/4/2011am
|
BMP Violation | 3/28/2011 | 3/28/2011 | 3/28/2011 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: CORRECTION NOTICE 1. Provide approved sotrm drain inlet protection on all storm drains. 2. Only non erodible materials are accepted on land bridges. Base rock is not an accepted method. 3. Provide a washout for all non storm water pollutants. Failure to comply with the notice within the given time frame will result in a stop work order. Will re-inspect on 3/30/2011am
|
General Inspection | 2/14/2011 | 2/14/2011 | 2/14/2011 | | PASS |
Dave Hannah
|
|
|
|
General Inspection | 12/29/2010 | 12/29/2010 | 1/3/2011 | | PASS |
Dave Hannah
|
|
|
|
Random Inspection | 11/5/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Dave Hannah
|
|
|
|
Random Inspection | 9/15/2010 | 9/15/2010 | 9/15/2010 | A | PASS |
Dave Hannah
|
|
|
|
Routing - Erosion and Sediment | 8/13/2010 | | 8/13/2010 | | PASS |
Clint A Smith
|
|
|
ESC10-00496 is also attached to BLD10-01853. Same area location as the project.
|
Site Preparation | 7/27/2010 | 8/2/2010 | 8/2/2010 | A | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 7/21/2010 | 7/27/2010 | 7/27/2010 | A | NR |
Clint A Smith
|
|
|
|
Site Preparation | 7/14/2010 | 7/21/2010 | 7/21/2010 | A | CANC |
Clint A Smith
|
|
|
No excavating has occured
|
Site Preparation | 7/14/2010 | 7/14/2010 | 7/14/2010 | | PART |
Clint A Smith
|
|
|
Excavating work will occur next week. Will re-inspect on 7/21/10.
|
Issue & PRINT permit COM | | | 7/7/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 6/28/2010 | | 6/28/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and the ESC permit conditions.
|
Application received | | | 6/17/2010 | | |
|
|
|
|