Site Final | 10/1/2010 | 10/5/2010 | 10/5/2010 | A | PASS |
Clint A Smith
|
|
|
###-#### Dan Smith
|
Site Final | 9/30/2010 | 10/1/2010 | 10/1/2010 | A | CANC |
Clint A Smith
|
|
|
Moved until 10/5/2010
|
Site Preparation | 9/14/2010 | 9/14/2010 | 9/14/2010 | | PASS |
Clint A Smith
|
|
|
At the end of the day, the bio filtration socks will be installed at the bottom of slope.
|
Routing - Erosion and Sediment | 9/7/2010 | | 9/7/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC Plan and ESC Permit conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2010 | | |
|
|
|
|
Telephone call | | | 9/7/2010 | | DONE |
|
|
|
left vm for bob at ###-####- permit ready and fees given
|
Permit Ready to Issue | | | 9/7/2010 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 9/7/2010 | | DONE |
|
|
|
|
Application received | | | 9/3/2010 | | |
|
|
|
|