Site Final | 6/23/2011 | 6/23/2011 | 6/23/2011 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 6/23/2011 | 6/23/2011 | 6/23/2011 | P | PASS |
Dave Hannah
|
|
|
|
General Inspection | 5/31/2011 | 5/31/2011 | 5/31/2011 | | DONE |
Daryl DeGrange
|
|
|
still under construction, job site is clean
|
General Inspection | 4/29/2011 | 4/29/2011 | 4/29/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/24/2011 | 3/24/2011 | 3/24/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/21/2011 | 2/21/2011 | 2/21/2011 | | CANC |
Clint A Smith
|
|
|
Holiday.
|
Random Inspection | 1/19/2011 | 1/19/2011 | 1/19/2011 | P | PASS |
Dave Hannah
|
|
|
|
Random Inspection | 1/18/2011 | 1/18/2011 | 1/18/2011 | P | PASS |
Dave Hannah
|
|
|
|
Site Preparation | 12/30/2010 | 1/6/2011 | 1/6/2011 | A | NR |
Clint A Smith
|
|
|
|
Site Preparation | 12/30/2010 | 12/30/2010 | 12/30/2010 | | NR |
Clint A Smith
|
|
|
|
Issue & PRINT permit SFD | | | 12/27/2010 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/29/2010 | | 11/29/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC Plan and ESC permit conditions.
|
Routing - Erosion and Sediment | 11/19/2010 | | 11/19/2010 | | FAIL |
Steven Webb
|
|
|
ESC plan is required since the ground distrubance is within 10 feet of the Boise City Canal.
|
Application received | | | 11/9/2010 | | |
|
|
|
|