General Inspection | 6/6/2011 | 6/6/2011 | 6/6/2011 | | DONE |
Daryl DeGrange
|
|
|
see final
|
Site Final | 6/6/2011 | 6/6/2011 | 6/6/2011 | A | PASS |
Daryl DeGrange
|
|
|
final ok landscaping in over 70% vegation
|
General Inspection | 5/6/2011 | 5/6/2011 | 5/6/2011 | | DONE |
Daryl DeGrange
|
|
|
|
Site Final | 5/6/2011 | 5/6/2011 | 5/6/2011 | P | CANC |
Daryl DeGrange
|
|
|
final ok over 70% vegetation coverage
|
General Inspection | 4/4/2011 | 4/5/2011 | 4/5/2011 | A | PASS |
Tony Young
|
|
|
|
General Inspection | 4/1/2011 | 4/1/2011 | 4/1/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/1/2011 | 3/1/2011 | 3/1/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 1/27/2011 | 1/27/2011 | 1/31/2011 | P | PASS |
Tony Young
|
|
|
|
General Inspection | 1/13/2011 | 1/13/2011 | 1/13/2011 | | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 12/10/2010 | 12/13/2010 | 12/13/2010 | P | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 12/8/2010 | 12/9/2010 | 12/10/2010 | A | DONE |
Clint A Smith
|
|
|
Duplicate.
|
Site Preparation | 12/8/2010 | 12/8/2010 | 12/10/2010 | P | DONE |
Clint A Smith
|
|
|
Duplicate.
|
Site Preparation | 12/10/2010 | 12/10/2010 | 12/10/2010 | | FAIL |
Clint A Smith
|
|
|
Correction Notice:(Verbal to RP) 1.Re-install all sediment barriers onsite per industry and manufactures specifications. 2. Clean up all sediment debris off of the hard surface. **Failure to comply within the given time frame will result in further enforcement. Will re-inspect on 12/13/2010PM
|
Site Preparation | 12/7/2010 | 12/8/2010 | 12/9/2010 | A | PASS |
Tony Young
|
|
|
|
Issue & PRINT permit SFD | | | 12/3/2010 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/29/2010 | | 11/29/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC Plan and ESC Permit Conditions.
|
Application received | | | 11/23/2010 | | |
|
|
|
|