Permit Information
Permit NumberESC11-00004
StatusFinaled
Name SCOTT HAWKER
Site Address 3417 W AMERICANA TERRACE
Project NameBOISE SKILLED NURSING
Customer Number 
ePlanReviewNo
Description
Trappers Island
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/15/20137/15/20137/15/2013 DONE
DetailsClint A Smith
DOC - Permit Finaled7/15/20137/15/20137/15/2013PPASS
DetailsClint A Smith
General Inspection6/13/20136/13/20136/13/2013 PART
DetailsClint A Smith
No activity
General Inspection5/13/20135/13/20135/13/2013 PASS
DetailsClint A Smith
General Inspection4/11/20134/11/20134/11/2013 PART
DetailsClint A Smith
General Inspection3/11/20133/11/20133/12/2013 PASS
DetailsKimberly M. Johnson
Site has been stabilized. The active portion of site on west side will return to Jay Walker's control when final stabilization is achieved for the surrounding areas of the building.
General Inspection2/7/20132/7/20132/7/2013 PASS
DetailsKimberly M. Johnson
Ref ESC10-00778 for site development inspection activities
General Inspection1/7/20131/7/20131/7/2013 PASS
DetailsClint A Smith
General Inspection12/7/201212/7/201212/7/2012 PASS
DetailsClint A Smith
BMP Violation11/5/201211/6/201211/6/2012PPASS
DetailsClint A Smith
General Inspection11/5/201211/5/201211/5/2012 FAIL
DetailsClint A Smith
Verbal to RP:
Contain the mortar mixers in the area where mortar mixers are staged. Also along the Boise River section of the project, must install all BMP's per the industry standards. Will re-inspect on 11/6/2012 PM
General Inspection10/4/201210/4/201210/5/2012 PASS
DetailsClint A Smith
General Inspection9/3/20129/3/20129/3/2012 CANC
DetailsSteven Webb
Holiday
General Inspection8/2/20128/2/20128/2/2012 PASS
DetailsClint A Smith
General Inspection7/2/20127/2/20127/2/2012 PASS
DetailsClint A Smith
General Inspection5/31/20125/31/20125/31/2012 PASS
DetailsClint A Smith
General Inspection4/30/20124/30/20124/30/2012 PASS
DetailsClint A Smith
General Inspection3/30/20123/30/20123/30/2012 PART
DetailsClint A Smith
Verbal to RP:
Provide maintenance to the concrete washout prior to the next pour date.
Random Inspection2/28/20122/28/20122/28/2012APASS
DetailsTom Arcoraci
General Inspection2/27/20122/27/20122/28/2012 PASS
DetailsTom Arcoraci
BMP Violation1/23/20121/27/20121/27/2012APART
DetailsClint A Smith
BMP's installed and maintained.
General Inspection1/20/20121/20/20121/23/2012 FAIL
DetailsClint A Smith
Verbal to RP:
Install additional sediment protection along the bottom of the top soil stockpile on the canal side. Maintain the perimeter sediment barriers along the Boise River side of the project. There are two areas where the sediment barrier is either being consumed by the stockpile and another part where there is a gap between the wattles. Will follow up on 1/27/2011 am.
General Inspection12/19/201112/20/201112/20/2011APASS
DetailsClint A Smith
Random Inspection12/19/201112/19/201112/19/2011PPART
DetailsTom Arcoraci
appears ok at this time
General Inspection11/18/201111/18/201111/18/2011 DONE
DetailsClint A Smith
Still in the land developement phase. No activity. Gate is locked.
General Inspection10/17/201110/17/201110/17/2011 PASS
DetailsClint A Smith
No activity today. Gate is locked to the project.
Random Inspection9/15/20119/15/20119/15/2011PPASS
DetailsClint A Smith
Walked the site with the Erosion Control company and verfgiied that all perimeter BMP's along the north site of the project atre installed correctly.
General Inspection9/1/20119/1/20119/1/2011PPART
DetailsClint A Smith
Verbal to RP:
Make sure that all straw wattles are installed per manufactures specifications. Install a temporary construction exit. Will follow up on 9/6/2011am.
Complaint Inspection8/30/20118/30/20118/30/2011APART
DetailsClint A Smith
Verbal to RP:
Due to the clearing and grubbing of the stock pile at the north east section of the project a sediment barrier need tobe installed to protect run off on to the ajacent property. Once the utility work is complete at the access, to provide a stabilized construction exit. Until that time to keep traffic to a minimum. Sweep un any sediment on the hard surface on a daily basis or if needed. Will follow up on 9/1/2011.
General Inspection8/29/20118/29/20118/29/2011 CANC
DetailsClint A Smith
Issue & PRINT permit COM  8/24/2011 DONE
DetailsTisha Gallop
Per Clint Smith ok to issue ESC permit prior to buidling permit
Routing - Erosion and Sediment8/23/2011 8/23/2011 PASS
DetailsClint A Smith
ESC plan approved with conditions attached to the permit.
Telephone call  8/23/2011 DONE
DetailsChristina Prado
Called Scott to let know permit is ready and fees due
Permit Ready to Issue  8/23/2011 DONE
DetailsChristina Prado
Routing - Erosion and Sediment1/19/2011 1/19/2011 FAIL
DetailsSteven Webb
ESC plan does not meet requirements according to the Plan Designer manual or BCC 8-17. ESC Plan Checklist sent to applicant and RP via e-mail. Re-submital is needed.
Application received  1/5/2011