Permit NumberESC11-00048
StatusFinaled
Name ISAAC WHITELEY
Site Address 1850 S TRAVERTINE WAY
Project NameNew Single Family Dwelling
Customer Number 
ePlanReviewNo
Description
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final9/29/20119/29/20119/30/2011PPASS
DetailsDave Hannah
DOC - Permit Finaled9/30/20119/30/20119/30/2011PPASS
DetailsDave Hannah
General Inspection9/12/20119/12/20119/12/2011 PASS
DetailsEric Strole
General Inspection8/11/20118/11/20118/11/2011 PASS
DetailsClint A Smith
General Inspection7/11/20117/11/20117/11/2011 FAIL
DetailsClint A Smith
Verbal to RP and Developer (Jeff Snyder):
Clean up all stucco wash out and piles. Provide a washout pit through the duration of the project, until the time when no non storm water pollutants need to be washed out. Will re-inspect on 7/13/2011AM.
General Inspection6/10/20116/10/20116/10/2011 PASS
DetailsClint A Smith
General Inspection5/10/20115/10/20115/10/2011 PASS
DetailsClint A Smith
General Inspection4/8/20114/8/20114/8/2011 FAIL
DetailsClint A Smith
Verbal to RP:
Imeadiately provide a concrete washout pit prior to the concrete trucks needing to clean out.
General Inspection3/8/20113/8/20113/8/2011 FAIL
DetailsClint A Smith
Verbal to Owner (Jeff Snyder)
provide a washout pit prior next time of any concrete pours. Also clean up all washed out concrete in the area where washout pit should be placed. Also maintain construction exit.
Issue & PRINT permit SFD  2/23/2011 DONE
General Inspection2/2/20112/2/20112/2/2011 PART
DetailsClint A Smith
Moved as a SITE PREPARATION.

Verbal to RP:
Install siltfence per industry standards or remove and replace wwith a different type of sediment barrier. Stop Work Order has been lifted.
Routing - Erosion and Sediment2/1/2011 2/1/2011 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and ESC permit conditions.
PLANS/APPL TAKEN TO FRONT DESK  2/1/2011  
Override - Parcel Holds  2/1/2011  
Issue & PRINT permit SFD  2/1/2011 DONE
Application received  1/31/2011 DONE
DetailsChristina Prado
Received two copies of required narratives for project. Routed to ESC for review
Routing - Erosion and Sediment1/28/2011 1/28/2011 FAIL
DetailsSteven Webb
ESC plan does not meet the requirements according to BMC8-17. Documents routed to ESC did not include the required narrative. Informed Plan Designer via telephone, (B. Semple). ESC documents are located in ESC "Pending Box".
Application received  1/27/2011