General Inspection | 6/22/2011 | 6/22/2011 | 6/22/2011 | | DONE |
Clint A Smith
|
|
|
PErmit finaled.
|
DOC - Permit Finaled | 6/22/2011 | 6/22/2011 | 6/22/2011 | P | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 4/18/2011 | 4/22/2011 | 4/22/2011 | A | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 4/12/2011 | 4/18/2011 | 4/18/2011 | A | NR |
Clint A Smith
|
|
|
|
Site Preparation | 3/16/2011 | 4/12/2011 | 4/12/2011 | A | NR |
Clint A Smith
|
|
|
|
General Inspection | 3/16/2011 | 3/16/2011 | 3/16/2011 | | NR |
Steven Webb
|
|
|
Talked to RP, Bob project scheduled to start the week of April 11, re-scheduled an inspection for 4/12 for inspector 460.
|
Issue & PRINT permit COM | | | 3/15/2011 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/7/2011 | | 2/7/2011 | | PASS |
Steven Webb
|
|
|
ESC plan waiver is approved according to the ESC permit conditions.
|
Application received | | | 1/31/2011 | | |
|
|
|
|