General Inspection | 4/13/2012 | 4/13/2012 | 4/13/2012 | | DONE |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 4/13/2012 | 4/13/2012 | 4/13/2012 | P | PASS |
Jim Storey
|
|
|
|
Site Final | 4/13/2012 | 4/13/2012 | 4/13/2012 | A | PASS |
Jim Storey
|
|
|
|
General Inspection | 2/12/2012 | 2/12/2012 | 2/12/2012 | | CANC |
Clint A Smith
|
|
|
Weekend
|
General Inspection | 12/12/2011 | 12/12/2011 | 12/12/2011 | | PASS |
Clint A Smith
|
|
|
Site stabilized. Waiting on vegitation.
|
General Inspection | 10/12/2011 | 10/12/2011 | 10/13/2011 | | PASS |
Eric Strole
|
|
|
bmp's in place, looks good.
|
General Inspection | 8/12/2011 | 8/12/2011 | 8/12/2011 | P | PART |
Clint A Smith
|
|
|
Hydroseeding complete.
|
Site Final | 7/25/2011 | 7/25/2011 | 7/25/2011 | A | PART |
Jim Storey
|
|
|
hydro seedding in place pending germanation.
|
Site Preparation | 6/20/2011 | 6/24/2011 | 6/23/2011 | A | PASS |
Clint A Smith
|
|
|
Will provide a washout pit prior to any cleaning out of non storm water pllutants.
|
General Inspection | 6/20/2011 | 6/20/2011 | 6/20/2011 | | DONE |
Clint A Smith
|
|
|
Went over project detils with RP and will follow up with a site prep on 6/24/2011AM
|
Issue & PRINT permit COM | | | 6/16/2011 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/9/2011 | | 6/9/2011 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions.
|
Application received | | | 5/31/2011 | | |
|
|
|
|