General Inspection | 2/27/2012 | 2/27/2012 | 3/27/2012 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 3/27/2012 | 3/27/2012 | 3/27/2012 | P | PASS |
Dave Hannah
|
|
|
|
General Inspection | 12/26/2011 | 12/26/2011 | 12/27/2011 | | CANC |
Steven Webb
|
|
|
Holiday
|
Site Preparation | 10/20/2011 | 10/20/2011 | 10/20/2011 | P | PART |
Clint A Smith
|
|
|
Verbal to RP: Re loacte the inlet protection from the street into the storm drain within the alley due to the construction traffic.
|
Issue & PRINT permit COM | | | 10/19/2011 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/28/2011 | | 6/28/2011 | | PASS |
Clint A Smith
|
|
|
ESC plan approved with conditions attached to the permit.
|
Routing - Erosion and Sediment | 6/23/2011 | | 6/23/2011 | | FAIL |
Clint A Smith
|
|
|
ESC plan faailed due to not submitting the narrative with the plan map. Contacted the applicant and also the plan designer of the requirements that area needed.
|
Application received | | | 6/15/2011 | | |
|
|
|
|