Permit Information
Permit NumberESC11-00517
StatusFinaled
Name CARL BENJAMIN
Site Address 401 S BROADWAY AVE
Project NameWhole Foods Market
Customer Number 
ePlanReviewNo
Description
Development and construction or Whole Foods on Block #1 (West Front & Broadway), as well, this permit includes development (no vertical structures) on future building site (Block 6) East Myrtle.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final11/8/201211/8/201211/8/2012APASS
DetailsDave Hannah
General Inspection10/26/201210/26/201210/26/2012 PASS
DetailsKimberly M. Johnson
General Inspection9/10/20129/10/20129/10/2012 PASS
DetailsClint A Smith
Telephone call  8/9/2012 DONE
DetailsTisha Gallop
received phone call from ESI to change RP from Vaughn Murinko to Carl Benjamin. They are with both with ESI just person on site changed.
BMP Violation7/24/20127/26/20127/26/2012APASS
DetailsClint A Smith
Random Inspection7/24/20127/24/20127/24/2012PFAIL
DetailsClint A Smith
Discussed with the Grading contractor to clean up al saw cut slurry off of the gutterpan on Myrtle St. Proir to me leaving, the contractor began to clean up the slurry. Will follow up on 7/26/2012
Conference7/10/20127/10/20127/11/2012A 
DetailsClint A Smith
Discussed with ESI over their notice of voilation they receivefrom EPA. We discussed over the 6 items of violation. I explained to them to quickly correct and respond back to EPA. Making sue that the response back to EPA shows all of the required supporting changes to the violation they received.
General Inspection6/11/20126/11/20126/11/2012 PASS
DetailsClint A Smith
General Inspection3/9/20123/9/20123/9/2012 PASS
DetailsClint A Smith


General Inspection1/23/20121/23/20121/23/2012 PASS
DetailsDaryl Spivey
General Inspection12/8/201112/8/201112/14/2011APASS
DetailsDave Hannah
General Inspection11/17/201111/17/201111/17/2011APASS
DetailsDave Hannah
Site Preparation10/21/201110/24/201110/24/2011PDONE
DetailsClint A Smith
Went over the project overview and BMP's placement and at time time when they will be utilized and installed.
Issue & PRINT permit COM  10/21/2011 DONE
DetailsBarbara Stitt
Application received  7/25/2011  
General Inspection4/24/20124/24/2012   
DetailsClint A Smith