Site Final | 7/25/2012 | 7/25/2012 | 7/25/2012 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 7/25/2012 | 7/25/2012 | 7/25/2012 | P | PASS |
Dave Hannah
|
|
|
|
BMP Violation | 7/16/2012 | 7/17/2012 | 7/17/2012 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 7/16/2012 | 7/16/2012 | 7/16/2012 | | PART |
Clint A Smith
|
|
|
Verbal to RP: (inspection was PART dueto the activities already being initiated.) Verbal to RP: Protect the stockpile along tthe back of sidewalk on Americana. Protect all storm drain inlets within the nterior of the newly paved area. Clean up the parking lot by the constrution trailer. Will re-inspect on 7/17/2012.
|
General Inspection | 5/29/2012 | 5/29/2012 | 5/30/2012 | | PASS |
Dave Hannah
|
|
|
|
General Inspection | 4/13/2012 | 4/13/2012 | 4/13/2012 | A | PASS |
Dave Hannah
|
|
|
|
General Inspection | 3/29/2012 | 3/29/2012 | 3/30/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/12/2012 | 2/12/2012 | 2/12/2012 | | CANC |
Clint A Smith
|
|
|
Weekend
|
General Inspection | 12/27/2011 | 12/27/2011 | 12/27/2011 | | PASS |
Steven Webb
|
|
|
site looks good. Have begun the vertical phase of the project.
|
Tracking Control | 11/8/2011 | 11/11/2011 | 11/9/2011 | P | PASS |
Clint A Smith
|
|
|
|
Complaint Inspection | 11/8/2011 | 11/8/2011 | 11/8/2011 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Extend the stabilized construction to minimum of 50 ft. CLean up all hard surfaces on a daily basis. Will follow up on 11/11/2011
|
Site Preparation | 9/20/2011 | 9/22/2011 | 9/22/2011 | A | PART |
Clint A Smith
|
|
|
Started to begin to stage equiptment.
|
General Inspection | 9/20/2011 | 9/20/2011 | 9/20/2011 | | NR |
Clint A Smith
|
|
|
|
Issue & PRINT permit COM | | | 9/15/2011 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/9/2011 | | 8/9/2011 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions.
|
Application received | | | 7/26/2011 | | |
|
|
|
|