General Inspection | 11/5/2012 | 11/5/2012 | 11/5/2012 | | DONE |
Clint A Smith
|
|
|
Permit finaled
|
DOC - Permit Finaled | 11/5/2012 | 11/5/2012 | 11/5/2012 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 9/3/2012 | 9/3/2012 | 9/3/2012 | | CANC |
Steven Webb
|
|
|
Holiday
|
General Inspection | 7/2/2012 | 7/2/2012 | 7/2/2012 | | PEND |
Tony Young
|
|
|
|
General Inspection | 4/30/2012 | 4/30/2012 | 4/30/2012 | | PASS |
Jim Johnson
|
|
|
|
General Inspection | 2/28/2012 | 2/28/2012 | 2/29/2012 | | PASS |
Jim Johnson
|
|
|
all equipment and stockpiles have been removed from area. area has been leveled, area is snow covered at this inspection not able to see any sign of stabilization of vegetation at this time
|
General Inspection | 12/28/2011 | 12/28/2011 | 12/30/2011 | | PEND |
Tony Young
|
|
|
|
Aging Inspection | 10/14/2011 | 10/14/2011 | 10/14/2011 | | PASS |
Clint A Smith
|
|
|
|
Tracking Control | 8/11/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 8/11/2011 | 8/11/2011 | 8/11/2011 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Post ESC sign where visable from the street. Re install the construction exit per industry standards. Min. 50ft in length, Min. 10ft wigth and make sur to have to 2in washed rock to begin at the back of the sidewalk. Will re-inspect on 8/15/2011
|
Stop Work Order | 8/5/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Steven Webb
|
|
|
Stop work place on site for working without a permit on August 3, 2011.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/5/2011 | | |
|
|
|
|
Permit Ready to Issue | | | 8/5/2011 | | DONE |
|
|
|
|
Telephone call | | | 8/5/2011 | | DONE |
|
|
|
8-5-11 called Jessie permit ready and fee given ///dld
|
Issue & PRINT permit COM | | | 8/5/2011 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/4/2011 | | 8/5/2011 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions.
|
Application received | | | 8/4/2011 | | |
|
|
|
|