Site Final | 2/7/2012 | 2/13/2012 | 2/13/2012 | A | DONE |
Jim Storey
|
|
|
in let protection needs removed
|
DOC - Permit Finaled | 2/13/2012 | 2/13/2012 | 2/13/2012 | P | PASS |
Jim Storey
|
|
|
|
Site Final | 2/6/2012 | 2/7/2012 | 2/7/2012 | P | PART |
Jim Storey
|
|
|
|
Site Final | 2/6/2012 | 2/6/2012 | 2/6/2012 | P | NR |
Jim Storey
|
|
|
|
Random Inspection | 12/6/2011 | 12/6/2011 | 12/6/2011 | P | PASS |
Jim Storey
|
|
|
|
General Inspection | 11/16/2011 | 11/18/2011 | 11/18/2011 | A | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 11/16/2011 | 11/16/2011 | 11/16/2011 | P | PART |
Clint A Smith
|
|
|
Verbal to RP: Provide storm drain inlet protection within the parking by the trash container. Will follow up on 11/18/2011
|
Issue & PRINT permit COM | | | 11/14/2011 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/27/2011 | | 10/27/2011 | | PASS |
Clint A Smith
|
|
|
ESC plan approved with attached conditions.
|
Routing - Erosion and Sediment | 10/25/2011 | | 10/25/2011 | | FAIL |
Clint A Smith
|
|
|
Application failed due to being a commercial project. The applicant must apply with an ESC plan developed by a current Boise City Certified Plan Designer or with a plan waiver. Left a message with the applicant over what requirements are needed.
|
Application received | | | 10/18/2011 | | |
|
|
|
|