General Inspection | 6/21/2012 | 6/21/2012 | 6/26/2012 | | PASS |
Bill VanDegrift
|
|
|
complete
|
Site Final | 6/26/2012 | 6/26/2012 | 6/26/2012 | A | PASS |
Bill VanDegrift
|
|
|
complete
|
General Inspection | 5/21/2012 | 5/21/2012 | 5/21/2012 | | PASS |
Daryl Spivey
|
|
|
|
General Inspection | 4/19/2012 | 4/19/2012 | 4/20/2012 | | PASS |
Tony Young
|
|
|
|
General Inspection | 3/19/2012 | 3/19/2012 | 3/19/2012 | | PASS |
Daryl Spivey
|
|
|
site clean. Wall is in and just need to re- vegetate to stabilize area for final...........ds
|
General Inspection | 2/15/2012 | 2/15/2012 | 2/17/2012 | | PASS |
Daryl Spivey
|
|
|
|
General Inspection | 1/15/2012 | 1/15/2012 | 1/17/2012 | | CANC |
Clint A Smith
|
|
|
Weekend
|
Site Preparation | 12/2/2011 | 12/2/2011 | 12/9/2011 | | PASS |
Daryl DeGrange
|
|
|
job site, gutters clean. wooden is down, conrete blocks on site
|
Routing - Erosion and Sediment | 11/28/2011 | | 11/29/2011 | | DONE |
Clint A Smith
|
|
|
ESC plan waiver approved with conditions attached to the permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2011 | | |
|
|
|
|
Permit Ready to Issue | | | 11/29/2011 | | DONE |
|
|
|
|
Telephone call | | | 11/29/2011 | | DONE |
Tisha Gallop
|
|
|
called Stan Leatham and told him permit is ready, fees already paid.
|
Issue & PRINT permit SFD | | | 11/29/2011 | | DONE |
|
|
|
|
Application received | | | 11/28/2011 | | |
|
|
|
|