General Inspection | 4/2/2012 | 4/2/2012 | 4/2/2012 | | DONE |
Clint A Smith
|
|
|
Permit finaled.
|
DOC - Permit Finaled | 4/2/2012 | 4/2/2012 | 4/2/2012 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/16/2012 | 3/16/2012 | 3/16/2012 | | PART |
Clint A Smith
|
|
|
Sprayed a seed & tachifier on all disturbed soil. Waiting on vegitation to establish to final permit.
|
General Inspection | 3/1/2012 | 3/1/2012 | 3/2/2012 | | CANC |
Clint A Smith
|
|
|
not at work
|
General Inspection | 2/15/2012 | 2/15/2012 | 2/15/2012 | | PART |
Clint A Smith
|
|
|
Need to acheive final stabilization.
|
Site Preparation | 1/30/2012 | 1/31/2012 | 2/1/2012 | A | PART |
Clint A Smith
|
|
|
Notified the Contractor (Jerry Wright) that he must remove all temporary BMP's and initiate stabilization measures as soon as practicable. Will follow up as soon as a date of hyrolic application will be initiated.
|
General Inspection | 1/30/2012 | 1/30/2012 | 1/30/2012 | | CANC |
Clint A Smith
|
|
|
Moved to a site preperation on 1/31/2012.
|
General Inspection | 1/15/2012 | 1/15/2012 | 1/17/2012 | | CANC |
Clint A Smith
|
|
|
Weekend
|
Routing - Erosion and Sediment | 12/7/2011 | | 12/7/2011 | | PASS |
Clint A Smith
|
|
|
ESC plan waiver approved woth conditions attached to the permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2011 | | |
|
|
|
|
Telephone call | | | 12/7/2011 | | DONE |
|
|
|
t/c w kathy - permit ready and fees given
|
Permit Ready to Issue | | | 12/7/2011 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 12/7/2011 | | DONE |
|
|
|
|
Application received | | | 12/6/2011 | | |
|
|
|
|