General Inspection | 2/11/2014 | 2/11/2014 | 2/11/2014 | | PASS |
Andy J. Long
|
|
|
Finaled. See notes.
|
DOC - Permit Finaled | 2/11/2014 | 2/11/2014 | 2/11/2014 | P | PASS |
Andy J. Long
|
|
|
Construction is complete on UV treatment plant. BLD permit final to be requested by contractor. All construction materials have been removed from staging. ESC conditions satisfied.
|
General Inspection | 1/27/2014 | 1/27/2014 | 1/27/2014 | | PASS |
Evan Jenkins
|
|
|
no issues at time of inspection
|
General Inspection | 1/10/2014 | 1/10/2014 | 1/10/2014 | | PASS |
Andy J. Long
|
|
|
Construction materials still on-site. No violations observed. Talked to WWTP contact Rob Anderson on-site and he confirmed that BLD final and ESC final will be called in January/early February. Minor interior work ongoing.
|
General Inspection | 12/26/2013 | 12/26/2013 | 12/26/2013 | | CANC |
Evan Jenkins
|
|
|
Called RP, they stated they will be calling in next week for a site final
|
General Inspection | 12/11/2013 | 12/11/2013 | 12/13/2013 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/26/2013 | 11/26/2013 | 11/26/2013 | | PASS |
Andy J. Long
|
|
|
Construction activity on-going. No corrections at this time. Will need to clean up contsruction materials in staging area when finished.
|
General Inspection | 11/11/2013 | 11/11/2013 | 11/12/2013 | | CANC |
Evan Jenkins
|
|
|
Holiday
|
General Inspection | 10/25/2013 | 10/25/2013 | 10/25/2013 | | PASS |
Andy J. Long
|
|
|
No ESC changes since previous inspection. WIP, no corrections at this time
|
General Inspection | 10/10/2013 | 10/10/2013 | 10/10/2013 | | PASS |
Andy J. Long
|
|
|
Project is still in progress. Work site contained in old earthen retention pond and is bermed. No ESC violations.
|
General Inspection | 9/10/2013 | 9/10/2013 | 9/10/2013 | | CANC |
Bill VanDegrift
|
|
|
needs to be done at final
|
General Inspection | 8/9/2013 | 8/9/2013 | 8/9/2013 | | CANC |
Kimberly M. Johnson
|
|
|
|
General Inspection | 7/25/2013 | 7/25/2013 | 7/25/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
General Inspection | 7/10/2013 | 7/10/2013 | 7/11/2013 | | PASS |
Clint A Smith
|
|
|
|
Site Final | 6/25/2013 | 6/25/2013 | 6/28/2013 | P | CANC |
Jim Sly
|
|
|
I scheduled this to do at Bldg final. Didn't go out on Bldg final.
|
General Inspection | 6/25/2013 | 6/25/2013 | 6/25/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/10/2013 | 6/10/2013 | 6/11/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/24/2013 | 5/24/2013 | 5/24/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/9/2013 | 5/9/2013 | 5/9/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 4/24/2013 | 4/24/2013 | 4/26/2013 | | NR |
Clint A Smith
|
|
|
No activity
|
Aging Inspection | 4/9/2013 | 4/9/2013 | 4/9/2013 | | DONE |
Clint A Smith
|
|
|
Waiting on BLD permit to be issued.
|
Change Status (ISS) | | | 4/8/2013 | | DONE |
Tisha Gallop
|
|
|
reopen permit per KMJ to cover Bld13-00093
|
General Inspection | 1/29/2013 | 1/29/2013 | 1/29/2013 | | DONE |
Clint A Smith
|
|
|
Permit finaled.
|
DOC - Permit Finaled | 1/29/2013 | 1/29/2013 | 1/29/2013 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 1/14/2013 | 1/14/2013 | 1/14/2013 | | PASS |
Clint A Smith
|
|
|
Work is complete, but due to contract agreements the staging area will be used for an extended period for the permited project.
|
General Inspection | 12/28/2012 | 12/28/2012 | 12/28/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 12/13/2012 | 12/13/2012 | 12/13/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 11/28/2012 | 11/28/2012 | 11/28/2012 | | PART |
Clint A Smith
|
|
|
MaintAIN CONCRETE WASHOUT
|
General Inspection | 11/13/2012 | 11/13/2012 | 11/13/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/29/2012 | 10/29/2012 | 10/29/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/12/2012 | 10/12/2012 | 10/9/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
General Inspection | 9/27/2012 | 9/27/2012 | 9/27/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 9/12/2012 | 9/12/2012 | 9/12/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 8/28/2012 | 8/28/2012 | 8/29/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 8/13/2012 | 8/13/2012 | 8/13/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 7/27/2012 | 7/27/2012 | 7/30/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
General Inspection | 7/12/2012 | 7/12/2012 | 7/13/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/27/2012 | 6/27/2012 | 6/27/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/12/2012 | 6/12/2012 | 6/14/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 4/25/2012 | 4/25/2012 | 4/26/2012 | | PART |
Clint A Smith
|
|
|
informed the inspector for public works to devert the discharge hose from the canal into the pasture once construction activies begin.
|
General Inspection | 3/23/2012 | 3/23/2012 | 3/23/2012 | P | PASS |
Jim Sly
|
|
|
|
Site Preparation | 3/8/2012 | 3/8/2012 | 3/12/2012 | | PASS |
Clint A Smith
|
|
|
|
Issue & PRINT permit COM | | | 3/5/2012 | | DONE |
|
|
|
|
Application received | | | 2/23/2012 | | |
|
|
|
|
Routing - Erosion and Sediment | 2/23/2012 | | 2/23/2012 | | PASS |
Clint A Smith
|
|
|
ESC plan approved with conditions attached to the permit.
|
General Inspection | 9/25/2013 | 9/25/2013 | | | |
Jim Sly
|
|
|
|
General Inspection | 8/26/2013 | 8/26/2013 | | | |
Jim Sly
|
|
|
|
General Inspection | 5/25/2012 | 5/25/2012 | | | |
Jim Sly
|
|
|
|
General Inspection | 5/10/2012 | 5/10/2012 | | | |
Jack Frank
|
|
|
|
General Inspection | 4/10/2012 | 4/10/2012 | | | |
Jim Sly
|
|
|
|
General Inspection | 3/23/2012 | 3/23/2012 | | | |
Jim Sly
|
|
|
|