Aging Inspection | 11/10/2014 | 11/10/2014 | 11/10/2014 | | PASS |
Andy J. Long
|
|
|
Abode subdivision development is fully constructed and nearly all lots are filled with completed homes. Harding Construction has several SFH permits active at this time and they will remove drop inlet filter bags.
No further ESC inspections necessary for this permit. Permit finaled.
|
DOC - Permit Finaled | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 9/8/2014 | 9/8/2014 | 9/8/2014 | | PASS |
Evan Jenkins
|
|
|
no issues at this time
|
Aging Inspection | 7/7/2014 | 7/7/2014 | 7/7/2014 | | PASS |
Andy J. Long
|
|
|
Abode sub development is complete. Will keep open to monitor condition of empty parcels. Only a few left.
|
Aging Inspection | 5/5/2014 | 5/5/2014 | 5/5/2014 | | PASS |
Andy J. Long
|
|
|
Abode Subdivision has several open lots remaining that have now vegetated. Utility trench in southwest corners is complete and filled in. DI bags have remaining filter capacity. No corrections at this time.
|
Aging Inspection | 3/3/2014 | 3/3/2014 | 3/3/2014 | | CANC |
Evan Jenkins
|
|
|
esc group out of town
|
Aging Inspection | 12/30/2013 | 12/30/2013 | 12/30/2013 | | FAIL |
Andy J. Long
|
|
|
Need to sweep street and gutters. Appears landscapers stockpiled sod or dirt on the sidewalk.
|
Aging Inspection | 10/28/2013 | 10/28/2013 | 10/28/2013 | | PASS |
Andy J. Long
|
|
|
Subdivision has been developed. Drop inlet bags in place while individual sites are under construction. Next inspection need to check bags, in condition currently.
|
Aging Inspection | 8/26/2013 | 8/26/2013 | 8/26/2013 | | PASS |
Eric Strole
|
|
|
|
General Inspection | 6/24/2013 | 6/24/2013 | 6/24/2013 | | CANC |
Kimberly M. Johnson
|
|
|
|
General Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 | | DONE |
Clint A Smith
|
|
|
No violations t this time but could not reach the listed RP
|
Aging Inspection | 2/19/2013 | 2/19/2013 | 2/20/2013 | | DONE |
Bob Reichert
|
|
|
no esc signs, perimeter barriers placed, some contamination on se walk, don't know rp
|
Telephone call | | | 1/2/2013 | | DONE |
|
|
|
Bob Shaw with development contacted me to inquire about RP transfer process. Will get back to me.
|
Site Preparation | 12/17/2012 | 12/21/2012 | 12/21/2012 | A | FAIL |
Clint A Smith
|
|
|
Developement is complete. All disturbed soil is not stabilized. The listed RP cound not be reached today. From the last conversation, the listed RP does not have day to day control of the project. We have not had a valid RP list yet on the porject.
|
General Inspection | 12/17/2012 | 12/17/2012 | 12/17/2012 | P | CANC |
Clint A Smith
|
|
|
Wrong date.
|
General Inspection | 12/17/2012 | 12/17/2012 | 12/17/2012 | | FAIL |
Clint A Smith
|
|
|
Explained that the conditions of the permit have not been achieved. Also explained that the filing of the N.O.T. must follow the CGP requirements. Must provide a valid RP and must maintain the perimeter controls at a minimum if temporary or perminate stabilization is not initiated.
|
General Inspection | 10/16/2012 | 10/16/2012 | 10/16/2012 | | NR |
Clint A Smith
|
|
|
|
General Inspection | 8/15/2012 | 8/15/2012 | 8/15/2012 | | PASS |
Clint A Smith
|
|
|
No activity.
|
Site Preparation | 6/15/2012 | 6/15/2012 | 6/22/2012 | | NR |
Clint A Smith
|
|
|
|
Issue & PRINT permit COM | | | 6/12/2012 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/7/2012 | | 6/8/2012 | | DONE |
Clint A Smith
|
|
|
ESC12-00447 plan approved with additional conditions attached to the permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2012 | | |
|
|
|
|
Permit Ready to Issue | | | 6/8/2012 | | |
|
|
|
|
Telephone call | | | 6/8/2012 | | |
|
|
|
6-8-12 called permit ready and fee given ///dld
|
Application received | | | 5/3/2012 | | |
|
|
|
|