General Inspection | 8/15/2013 | 8/15/2013 | 8/15/2013 | | PASS |
Tom Arcoraci
|
|
|
|
Site Final | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
General Inspection | 7/15/2013 | 7/15/2013 | 7/15/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/14/2013 | 6/14/2013 | 6/14/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/14/2013 | 5/14/2013 | 5/15/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 1/25/2013 | 1/25/2013 | 1/28/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 12/25/2012 | 12/25/2012 | 12/26/2012 | | CANC |
Clint A Smith
|
|
|
Holiday
|
General Inspection | 11/22/2012 | 11/22/2012 | 11/23/2012 | | CANC |
Kimberly M. Johnson
|
|
|
Holiday
|
General Inspection | 10/22/2012 | 10/22/2012 | 10/22/2012 | | PASS |
Tom Arcoraci
|
|
|
wip ok
|
General Inspection | 9/19/2012 | 9/19/2012 | 9/19/2012 | | PART |
Clint A Smith
|
|
|
Need to post ESC sign
|
Site Preparation | 8/16/2012 | 8/16/2012 | 8/17/2012 | | NR |
Clint A Smith
|
|
|
|
Issue & PRINT permit SFD | | | 8/13/2012 | | DONE |
|
|
|
|
Application received | | | 8/1/2012 | | |
|
|
|
|
Routing - Erosion and Sediment | 8/1/2012 | | 8/1/2012 | | PASS |
Kimberly M. Johnson
|
|
|
Approved per conditions
|
General Inspection | 4/12/2013 | 4/12/2013 | | | |
Tom Arcoraci
|
|
|
|
General Inspection | 2/25/2013 | 3/12/2013 | | | |