General Inspection | 7/12/2013 | 7/12/2013 | 7/12/2013 | | DONE |
Clint A Smith
|
|
|
|
DOC - Permit Finaled | 7/12/2013 | 7/12/2013 | 7/12/2013 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/27/2013 | 5/27/2013 | 5/28/2013 | | CANC |
Kimberly M. Johnson
|
|
|
Holiday
|
General Inspection | 4/9/2013 | 4/9/2013 | 4/10/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/19/2013 | 2/19/2013 | 2/20/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 1/4/2013 | 1/4/2013 | 1/4/2013 | | PASS |
Clint A Smith
|
|
|
No activity due to the freeze
|
BMP Violation | 11/16/2012 | 11/19/2012 | 11/19/2012 | A | PASS |
Clint A Smith
|
|
|
|
Random Inspection | 11/16/2012 | 11/16/2012 | 11/16/2012 | P | FAIL |
Clint A Smith
|
|
|
Verbal to Super: (RP out of town) Protect the three other storm drain not shown on plans. Clean up all sediment off of he hard surfaces at the end of the working day. Will re-inspect on 11/19/2012
|
Site Preparation | 11/5/2012 | 11/6/2012 | 11/6/2012 | A | PASS |
Jim Sly
|
|
|
Sign up, inlet protections in place, concrete wash out area being dug now.......appears OK.
|
Site Preparation | 10/15/2012 | 10/15/2012 | 10/15/2012 | | NR |
Kimberly M. Johnson
|
|
|
|
Issue & PRINT permit COM | | | 10/12/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Erosion and Sediment | 9/12/2012 | | 9/12/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Application received | | | 8/31/2012 | | |
|
|
|
|