Permit Information
Permit NumberESC12-00929
StatusFinaled
Name SETH RADFORD
Site Address 11818 W JOPLIN RD
Project NameWest Boise WWFT Greenbelt Expa
Customer Number 
ePlanReviewNo
Description
West Boise WWTF Greenbelt Expansion. Project scope amended to include paving greenbelt path
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection3/27/20133/27/20133/27/2013 DONE
DetailsClint A Smith
Permit finaled
DOC - Permit Finaled3/27/20133/27/20133/27/2013PPASS
DetailsClint A Smith
General Inspection3/12/20133/12/20133/14/2013 PART
DetailsKimberly M. Johnson
No veg yet
General Inspection2/22/20132/22/20132/22/2013 PART
DetailsClint A Smith
Waiting on vegitation to setablish.
General Inspection2/7/20132/7/20132/7/2013 PART
DetailsClint A Smith
Waiting on vegitation to setablish.
General Inspection1/23/20131/23/20131/23/2013 PART
DetailsClint A Smith
Waiting on thaw to final out the permti.
General Inspection1/8/20131/8/20131/8/2013 PART
DetailsClint A Smith
Temporary stabilization methods applied prior to the winter. Site is covered in snow.
General Inspection12/21/201212/21/201212/21/2012 PASS
DetailsClint A Smith
All area of disturbed soil have had mulch, seed and tachifier applied.
Conference12/5/201212/6/201212/12/2012PCANC
DetailsClint A Smith
test permit
General Inspection12/5/201212/5/201212/5/2012 PASS
DetailsClint A Smith
Will be inspecting the project with the RP to address any area that still need to be staabilized on 12/6/2012
General Inspection11/20/201211/20/201211/20/2012 PART
DetailsClint A Smith
Must maintain concrete washout prior to next pour in the Spring time of 2013
BMP Violation10/30/201211/2/201211/2/2012APART
DetailsClint A Smith
Discussed with the RP over stabilization practices and that compacted pitrun is not considered an acceptable stabilization practice.
BMP Violation10/26/201210/30/201210/30/2012ACANC
DetailsClint A Smith
Re sheduled for 11/2/2012
General Inspection10/24/201210/24/201210/26/2012 FAIL
DetailsClint A Smith
Verbal to RP:
Maintain sediment controls along the west end of the project area. Will re-inspect on 10/30/2012
Routing - Erosion and Sediment10/18/2012 10/18/2012 PASS
DetailsKimberly M. Johnson
additional scope of work to pave the path.
Random Inspection10/9/201210/9/201210/9/2012PPART
DetailsKimberly M. Johnson
BMPs not sufficient in narrow areas. Blade for grading too wide and soil was being pushed on top of and some instances over the the wattle. Contractor had already called out RP group to widen perimeter controls to edge of disturbance (barb wire fence line) and to install sandbags along narrow areas where height of wattle is not sufficient.
General Inspection10/3/201210/4/201210/5/2012PPASS
DetailsClint A Smith
General Inspection10/3/201210/3/201210/3/2012PCANC
DetailsClint A Smith
no activity
General Inspection10/2/201210/3/201210/3/2012ADONE
DetailsClint A Smith
Went over certain points of concerns with the project along the Boise River side. Also explained to the contractor (Syman Company) over deficencies with the installtion of the sediment barriers being installed incorrectly. Will follow up this afternoon.
Site Preparation10/1/201210/1/201210/2/2012 PART
DetailsClint A Smith
WOrking with he ESC contractor, we discussed over the area on the ESC plan where it was impossible for the installation of a "trenched" sediment barrier. Told the contractor to look at other options like "weighted" products. Will follow up on 10/3/2012AM.
Issue & PRINT permit COM  9/28/2012 DONE
Routing - Erosion and Sediment9/24/2012 9/24/2012 PASS
DetailsKimberly M. Johnson
Routing - Erosion and Sediment9/11/2012 9/12/2012 FAIL
DetailsKimberly M. Johnson
Met with contractor and plan designer to walk the site. Plan needs revised with correct disturbance limits and the addition of BMPs where construction is within 50 feet of the river, as discussed during the site visit conference.
Application received  9/11/2012