General Inspection | 9/5/2013 | 9/5/2013 | 9/10/2013 | | PASS |
Bill VanDegrift
|
|
|
|
Site Final | 9/10/2013 | 9/10/2013 | 9/10/2013 | P | PASS |
Bill VanDegrift
|
|
|
|
General Inspection | 8/5/2013 | 8/5/2013 | 8/5/2013 | | PASS |
Rock A. Hudson
|
|
|
|
General Inspection | 7/4/2013 | 7/4/2013 | 7/5/2013 | | CANC |
Clint A Smith
|
|
|
Holiday
|
General Inspection | 6/3/2013 | 6/3/2013 | 6/3/2013 | | NR |
Clint A Smith
|
|
|
|
General Inspection | 5/1/2013 | 5/1/2013 | 5/1/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/27/2013 | 3/27/2013 | 3/27/2013 | | PASS |
Rock A. Hudson
|
|
|
|
Site Preparation | 2/20/2013 | 2/22/2013 | 2/22/2013 | A | PASS |
Rock A. Hudson
|
|
|
Check storm drain protection Done
|
General Inspection | 2/19/2013 | 2/19/2013 | 2/20/2013 | | FAIL |
Rock A. Hudson
|
|
|
8-17-02.4 E,J. Storm drain protection needed. Contacted RP Adam Vissotski and left message. will schedule reinspection.
|
General Inspection | 1/16/2013 | 1/16/2013 | 1/16/2013 | | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 12/13/2012 | 12/13/2012 | 12/13/2012 | | PASS |
Rock A. Hudson
|
|
|
Perimeter sediment fence in place. Have not broke ground yet. ESC sign posted.
|
Issue & PRINT permit SFD | | | 12/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Erosion and Sediment | 11/27/2012 | | 11/27/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Application received | | | 11/19/2012 | | |
|
|
|
|