DOC - Permit Finaled | 1/8/2014 | 1/8/2014 | 1/8/2014 | P | PASS |
Andy J. Long
|
|
|
Unpaved area to the west of the Jack in the Box parking lot was previously a dirt lot before construction and was not part of project. Although on same parcel, it was not part of the area of disturbance. The lot has been graded and 3/4 inch gravel placed on the lot for stabilization in early December 2013. ESC conditions satisfied.
|
Site Final | 1/7/2014 | 1/8/2014 | 1/8/2014 | A | PASS |
Andy J. Long
|
|
|
Site final requested. Chris Collete - Radix Construction ph # ###-####
Finaled. Please see activity notes.
|
General Inspection | 12/30/2013 | 12/30/2013 | 12/30/2013 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/12/2013 | 11/12/2013 | 11/12/2013 | | PART |
Andy J. Long
|
|
|
Jack in the Box is open for business and has a temporary C of O. The adjacent dirt lot is graded but there is no activity. The lot needs stabilization or restricted access to prevent track out to parking lot and street. See activity notes
|
Site Final | 9/26/2013 | 9/27/2013 | 9/27/2013 | P | NR |
Jim Sly
|
|
|
Steve phone Need to Stabilize all surronding disturbed areas.
|
Site Final | 9/25/2013 | 9/26/2013 | 9/26/2013 | P | NR |
Jim Sly
|
|
|
Steve phone
|
Site Final | 9/25/2013 | 9/25/2013 | 9/25/2013 | P | CANC |
Jim Sly
|
|
|
Tony phone
|
Site Final | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | NR |
Jim Sly
|
|
|
|
General Inspection | 9/16/2013 | 9/16/2013 | 9/16/2013 | | PASS |
Alan Hauser
|
|
|
|
General Inspection | 7/30/2013 | 7/30/2013 | 8/1/2013 | | PART |
Kimberly M. Johnson
|
|
|
Met superintendent on site (Rick). Must adequately protect canal located on north side of property. Canal was not identified on plan set. Discussed with Rick the need to identify owner of canal company to ask what needs done within the canal co easement. Must install one more DI BMP on Maple Grove. Had DIs protected on Fairview and one on Maple Grove.
|
Site Preparation | 6/13/2013 | 6/13/2013 | 6/13/2013 | | PASS |
Clint A Smith
|
|
|
|
Issue & PRINT permit COM | | | 6/10/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/6/2013 | | 6/6/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - Erosion and Sediment | 5/3/2013 | | 5/6/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
Plan modification submitted. The Erosion Control Plan was approved on March 11, 2013 with redlines. Please resubmit this plan with those redlines included.
Please confirm the total disturbance area. The application and Erosion Control Plan both indicate the project will disturb 0.68 acres, however the map C5.1 states 1.17 acres will be disturbed.
|
Routing - Erosion and Sediment | 12/18/2012 | | 3/11/2013 | | PASS |
Kimberly M. Johnson
|
|
|
approved with redlines
|
Application received | | | 12/21/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 21 2012 6:48PM
|