General Inspection | 6/12/2013 | 6/12/2013 | 6/13/2013 | | PASS |
Kimberly M. Johnson
|
|
|
finaled
|
DOC - Permit Finaled | 6/13/2013 | 6/13/2013 | 6/13/2013 | P | PASS |
Kimberly M. Johnson
|
|
|
|
Site Final | 4/25/2013 | 5/25/2013 | 5/20/2013 | A | FAIL |
Clint A Smith
|
|
|
Once the swale has established vegitation, then the permit can be finaled out.
|
Site Final | 4/25/2013 | 4/25/2013 | 4/25/2013 | P | FAIL |
Clint A Smith
|
|
|
Need to achieve vegetation in the portions where hydroseeding was applied.
|
General Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 | | PART |
Clint A Smith
|
|
|
Verbal to Tuffy Excavation; Provide a pipe where the ramp has been installed to keep the storm flow from being impacted. Provide a proper washout prior to any concrete work occuring.
|
Issue & PRINT permit COM | | | 4/4/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/13/2013 | | 2/14/2013 | | PASS |
Kimberly M. Johnson
|
|
|
approved with redlines
|
Application received | | | 2/11/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 11 2013 11:24AM
|