Site Final | 12/5/2013 | 12/5/2013 | 12/5/2013 | P | PASS |
Evan Jenkins
|
|
|
dan Phone #: ###-#### see final
|
DOC - Permit Finaled | 12/5/2013 | 12/5/2013 | 12/5/2013 | P | PASS |
Evan Jenkins
|
|
|
Construction still ongoing Will not disturb vegetation
|
General Inspection | 10/30/2013 | 10/30/2013 | 10/30/2013 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 9/11/2013 | 9/11/2013 | 9/11/2013 | | PASS |
Daryl Spivey
|
|
|
|
General Inspection | 7/24/2013 | 7/24/2013 | 7/24/2013 | P | PART |
Kimberly M. Johnson
|
|
|
Verbal to RP: Stabilize stockpile in back; write in correct. DI along Woody has filter fabric; will need approved DI protection before rainy season. Filter fabric in DI must be replaced with approved DI BMP if construction is still active in rainy season; okay for now. Job site is clean.
|
Site Preparation | 6/3/2013 | 6/3/2013 | 6/4/2013 | P | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 5/16/2013 | 5/16/2013 | 5/16/2013 | | PASS |
Clint A Smith
|
|
|
|
Override - Parcel Holds | | | 5/13/2013 | | |
|
|
|
|
Override - Parcel Holds | | | 5/13/2013 | | |
|
|
|
|
Override - Parcel Holds | | | 5/13/2013 | | |
|
|
|
|
Issue & PRINT permit SFD | | | 5/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Erosion and Sediment | 4/19/2013 | | 4/19/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Approved per redlines. Note, plan does not meet federal SWPPP requirements
|
Application received | | | 4/3/2013 | | |
|
|
|
|