DOC - Permit Finaled | 4/24/2014 | 4/24/2014 | 4/24/2014 | P | PASS |
Andy J. Long
|
|
|
Grading and drainage complete for thrift store. All permits for project finaled. Open for business. ESC conditions satisfied.
|
General Inspection | 3/18/2014 | 3/18/2014 | 3/18/2014 | | PASS |
Andy J. Long
|
|
|
Thrift store near completion. Parking lot and surround area is paved. No corrections required.
|
General Inspection | 1/31/2014 | 1/31/2014 | 1/31/2014 | | PASS |
Andy J. Long
|
|
|
Earthwork and utility trenching through existing parking lot is complete. No trackout, discharges, or other violations observed
|
General Inspection | 12/16/2013 | 12/16/2013 | 12/16/2013 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/30/2013 | 10/30/2013 | 10/30/2013 | | PASS |
Andy J. Long
|
|
|
Construction on corner of Franklin and Auto. WIP. No corrections at this time.
|
General Inspection | 9/11/2013 | 9/11/2013 | 9/11/2013 | | PASS |
Bill VanDegrift
|
|
|
|
Random Inspection | 7/26/2013 | 7/26/2013 | 7/26/2013 | P | PART |
Kimberly M. Johnson
|
|
|
Post ESC sign. sediment control will need installed around subsoil stockpile before next forecasted rain event
|
General Inspection | 7/12/2013 | 7/12/2013 | 7/12/2013 | | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 5/27/2013 | 5/27/2013 | 5/28/2013 | | CANC |
Kimberly M. Johnson
|
|
|
Holiday
|
Issue & PRINT permit COM | | | 5/24/2013 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2013 | | |
|
|
|
|
Routing - Erosion and Sediment | 4/16/2013 | | 4/16/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Must meet grading and drainage requirements before issueing. LM for Jim Coslett 4/17
|
Application received | | | 4/15/2013 | | |
|
|
|
|