Site Final | 10/28/2014 | 10/28/2014 | 10/28/2014 | P | PASS |
Andy J. Long
|
|
|
All construction at Depot Lofts is complete (2 apt. buildings, carports, garage) and construction materials have been removed from site. Temporary BMPs have been removed. Parking lot was swept clean and common areas are landscaped. ESC permit conditions satisfied.
|
DOC - Permit Finaled | 10/28/2014 | 10/28/2014 | 10/28/2014 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 | | PASS |
Andy J. Long
|
|
|
Depot Lofts' buildings are complete, common areas landscaped. Some BLD permits for project are open, so will continue to inspect at this time. There is some demolition of old structures on adjacent lot that I needs investigation.
|
Random Inspection | 7/31/2014 | 7/31/2014 | 7/31/2014 | P | PART |
Andy J. Long
|
|
|
Depot Lofts' apartment buildings are complete and the paving and curb work has been installed in the parking loft.
Construction on The newly installed storm drain drop inlets will need protection during further construction of the 3 carports that will now be covered under this permit.
Correction:
Need to sweep parking and remove construction supplies that are no longer in use.
No discharges or erosion issues observed. Site has been landscaped.
|
General Inspection | 7/8/2014 | 7/8/2014 | 7/8/2014 | | PASS |
Evan Jenkins
|
|
|
Project near completion Parking lot has been paved. Landscaping still needs to be completed No ESC Issues at time of inspection
|
General Inspection | 5/23/2014 | 5/23/2014 | 5/23/2014 | | PART |
Evan Jenkins
|
|
|
Some minimal trackout. Talked with Contractor, he stated he has been sweeping about every two days. I told him he should sweep after each day to reduce dust. He stated he will, and that they are prepping to pave next week.
|
Tracking Control | 4/7/2014 | 4/7/2014 | 4/7/2014 | P | PART |
Andy J. Long
|
|
|
Some minor trackout onto Victoria. No adjacent MS4s but does need some sweeping. The parking lot is to be installed within the next 2 weeks so that will help.
Discussed issue with contractor Dan (inside trailor) who stated he will get the entrance swept and monitor track out.
|
Conference | 3/10/2014 | 3/10/2014 | 3/10/2014 | A | DONE |
Evan Jenkins
|
|
|
Meeting w/ Fire Dept. to discuss potential of access road for Fire Department. Also, address trackout issues and construction entrance FIRE DEPT. DIDN'T SHOW UP. CONTRACTOR TO REINSTALL CONSTRUCTION ENTRANCE AND SWEEP TRACKOUT
|
General Inspection | 1/24/2014 | 1/24/2014 | 1/24/2014 | | PASS |
Evan Jenkins
|
|
|
no violations at time of inspection work in progress
|
General Inspection | 12/9/2013 | 12/9/2013 | 12/9/2013 | | PASS |
Evan Jenkins
|
|
|
Frozen; no construction activity other than power line work
|
General Inspection | 10/22/2013 | 10/22/2013 | 10/22/2013 | | PASS |
Andy J. Long
|
|
|
Does not have discharge to MS4. Permit posted. Application received prior to site prep inspection requirement. No violations at time of inspection.
|
Issue & PRINT permit COM | | | 10/15/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/16/2013 | | 5/16/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Plan approved. Noted on plan that it does not meet federal SWPPP requirements
|
Application received | | | 4/30/2013 | | |
|
|
|
|