Site Final | 3/25/2014 | 3/25/2014 | 3/25/2014 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 3/25/2014 | 3/25/2014 | 3/25/2014 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 3/25/2014 | 3/25/2014 | 3/25/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/7/2014 | 2/7/2014 | 2/7/2014 | | PASS |
Andy J. Long
|
|
|
No corrections required. No trackout or illicit stockpiles observed.
|
General Inspection | 12/23/2013 | 12/23/2013 | 12/23/2013 | | PASS |
Andy J. Long
|
|
|
No new violations observed at Union Square. Corrections issued Friday 12/20 have been addressed.
|
General Inspection | 11/5/2013 | 11/5/2013 | 11/5/2013 | | PASS |
Evan Jenkins
|
|
|
|
Random Inspection | 8/5/2013 | 8/5/2013 | 8/5/2013 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 7/18/2013 | 7/18/2013 | 7/18/2013 | | PASS |
Clint A Smith
|
|
|
|
Issue & PRINT permit COM | | | 6/26/2013 | | |
|
|
|
|
Routing - Erosion and Sediment | 6/19/2013 | | 6/20/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Approved in EPlan as noted:
1. The City of Boise requires BMPs are put in place to protect the porous pavement.
2. Section 2.5 lists the anticipated non stormwater discharges. These discharges are allowed but must be kept clean. Discharges to the MS4 system (any storm drain owned by ACHD) must first obtain a dewatering permit from ACHD.
3. Additional 0.62 acre staging area on north side of Smoke Ranch Drive was approved 6/20/2013
|
Routing - Erosion and Sediment | 5/30/2013 | | 6/3/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Approved as noted: 1. The City of Boise requires BMPs are put in place to protect the porous pavement once installed. Phase I of the Union Square Apartments is familiar with this practice and currently uses plastic sheeting and gravel bags or scrap wood to secure it. This practice helps to avoid the need for premature maintenance on the stormwater system.
2. Section 2.5 lists the anticipated non stormwater discharges. These discharges are allowed but must be kept clean. Discharges to the MS4 system (any storm drain owned by ACHD) must first obtain a dewatering permit from ACHD.
|
Application received | | | 5/21/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2013 4:20PM
|
General Inspection | 9/20/2013 | 9/20/2013 | | | |
Mike Jordan
|
|
|
|