General Inspection | 4/14/2014 | 4/14/2014 | 4/14/2014 | | PASS |
Andy J. Long
|
|
|
Finaled. BLD permit still open.
|
DOC - Permit Finaled | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | PASS |
Andy J. Long
|
|
|
Drive-thru renovation complete and in operation.. BMPs removed. ESC permit conditions satisfied.
|
General Inspection | 12/10/2013 | 12/10/2013 | 12/10/2013 | | PASS |
Andy J. Long
|
|
|
Some minor phases of project remains. Curbing and landscaping are complete. No stockpiles/undisturbed dirt on site. No corrections required.
|
General Inspection | 10/9/2013 | 10/9/2013 | 10/9/2013 | | PASS |
Andy J. Long
|
|
|
Perimeter wattles installed. Parking lot area surrounding drive thru work is well swept. No activity during inspection, but project is not complete.
|
Routing - Erosion and Sediment | 9/30/2013 | | 9/30/2013 | | DONE |
Evan Jenkins
|
|
|
|
General Inspection | 8/7/2013 | 8/7/2013 | 8/7/2013 | | PASS |
Bill VanDegrift
|
|
|
protection in place
|
Issue & PRINT permit COM | | | 7/9/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/11/2013 | | 6/13/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Permit Ready to Issue | | | 6/10/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/29/2013 | | |
|
|
|
|
General Inspection | 2/10/2014 | 2/10/2014 | | | |
Mike Jordan
|
|
|
|