Tracking Control | 10/29/2013 | 10/30/2013 | 11/1/2013 | A | CANC |
Evan Jenkins
|
|
|
|
Site Final | 10/31/2013 | 10/31/2013 | 10/31/2013 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 10/31/2013 | 10/31/2013 | 10/31/2013 | P | PASS |
Dave Hannah
|
|
|
|
General Inspection | 10/29/2013 | 10/29/2013 | 10/29/2013 | P | FAIL |
Evan Jenkins
|
|
|
Excessive Trackout No BMP's in place off hillside Verbal Correction Notice to RP via cell call. Sweep Streets, install BMP's. RP stated he will get it swept up by end of day, and bare soils sprayed and sodded today. (Prep Work currently)
|
General Inspection | 10/16/2013 | 10/16/2013 | 10/16/2013 | | PASS |
Andy J. Long
|
|
|
WIP. Pouring driveway. Stockpiles have permeter BMPs. No trackout at time of inspection.
|
General Inspection | 9/13/2013 | 9/13/2013 | 9/13/2013 | | PASS |
Bill VanDegrift
|
|
|
|
General Inspection | 8/7/2013 | 8/7/2013 | 8/14/2013 | | PASS |
Eric Strole
|
|
|
|
BMP Violation | 6/19/2013 | 6/21/2013 | 6/21/2013 | P | PASS |
Kimberly M. Johnson
|
|
|
|
Site Preparation | 6/19/2013 | 6/19/2013 | 6/19/2013 | P | FAIL |
Kimberly M. Johnson
|
|
|
Sediment controls and construction access need installed. Dirt haul out expected to be completed 6/20.
|
Issue & PRINT permit SFD | | | 6/17/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/4/2013 | | 6/4/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Application received | | | 5/29/2013 | | |
|
|
|
|