Site Final | 12/9/2014 | 12/9/2014 | 12/10/2014 | A | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Mike Jordan
|
|
|
|
Aging Inspection | 11/24/2014 | 11/24/2014 | 11/24/2014 | | PASS |
Andy J. Long
|
|
|
Staging trailers are still on site and interior work in progress. No exterior excavation or disturbance. No stormwater pollution sources observed at time of inspection. No corrections at this time. Should be getting close to completion.
|
Aging Inspection | 9/22/2014 | 9/22/2014 | 9/22/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/21/2014 | 7/21/2014 | 7/21/2014 | | PASS |
Andy J. Long
|
|
|
Interior work still ongoing. Staging area along back access drive will need to be swept at end of work.
Receiving storm drain has inlet protection.
|
Random Inspection | 5/21/2014 | 5/21/2014 | 5/21/2014 | A | PASS |
Mike Jordan
|
|
|
|
General Inspection | 3/31/2014 | 3/31/2014 | 3/31/2014 | A | PASS |
Mike Jordan
|
|
|
|
Aging Inspection | 3/11/2014 | 3/11/2014 | 3/11/2014 | | PASS |
Andy J. Long
|
|
|
WIP. BMPs installed. No corrections at this time.
|
General Inspection | 1/7/2014 | 1/7/2014 | 1/7/2014 | | PASS |
Alan Hauser
|
|
|
|
Random Inspection | 11/4/2013 | 11/4/2013 | 11/4/2013 | A | PASS |
Mike Jordan
|
|
|
|
General Inspection | 10/9/2013 | 10/9/2013 | 10/9/2013 | | NR |
Andy J. Long
|
|
|
This permit is for phase II of work at Treasure Valley Hospital. The project is still in phase I and coverered with ESC13-00561.
|
Permit Ready to Issue | | | 7/2/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/26/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 26 2013 2:30PM
|