General Inspection | 8/2/2016 | 8/2/2016 | 8/2/2016 | | PASS |
Andy J. Long
|
|
|
No further subdivsion development construction work is needed at Antelope Springs. Site has permanent stormwater facilities & treatment installed. Slopes within project are vegetated and stabilized.
Remaining SFHs will be inspected on individual ESC permits. No further inspections on this permit. Permit condtions and stabilization requirements have been met.
Builders shall be responsible for the sediment filter bags installed, which are in good condition.
|
DOC - Permit Finaled | 8/2/2016 | 8/2/2016 | 8/2/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/18/2016 | 7/18/2016 | 7/19/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/1/2016 | 7/1/2016 | 7/1/2016 | | PASS |
Andy J. Long
|
|
|
No subidivision work occuring, lots stabilized and permanent stormwater controls installed. DI bag installed. One SFH is active and near completion. Site should be assessed for site final next inspection..
|
General Inspection | 6/16/2016 | 6/16/2016 | 6/16/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/1/2016 | 6/1/2016 | 6/1/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/17/2016 | 5/17/2016 | 5/17/2016 | | PASS |
Evan Jenkins
|
|
|
very minor work occuring at newer subdivision. no issues observed
|
General Inspection | 5/2/2016 | 5/2/2016 | 5/2/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/15/2016 | 4/15/2016 | 4/15/2016 | | PASS |
Evan Jenkins
|
|
|
Currently 1 home under construction. 1 home needs landscaping performed. No ESC issues observed
|
General Inspection | 3/31/2016 | 3/31/2016 | 3/31/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/16/2016 | 3/16/2016 | 3/16/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/15/2016 | 2/15/2016 | 2/16/2016 | | PASS |
Andy J. Long
|
|
|
WIP on 2 active SFHs by different builders. Most lots now occpied. No trackout from subdivision. Site perimeter and permanent stormwater facilities installed and have sediment protection (DI bags)
|
General Inspection | 1/29/2016 | 1/29/2016 | 1/29/2016 | | PART |
Evan Jenkins
|
|
|
|
General Inspection | 1/14/2016 | 1/14/2016 | 1/14/2016 | | PASS |
Andy J. Long
|
|
|
No discharges or trackout out of subdivision. Several SFHs in progress. Streets will need to be swept when conditions dry. Storm drains have sediment bags installed. Approved.
|
General Inspection | 12/30/2015 | 12/30/2015 | 12/31/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 12/15/2015 | 12/15/2015 | 12/15/2015 | | PASS |
Evan Jenkins
|
|
|
WIP on a few SFH's. No ESC issues observed
|
General Inspection | 11/30/2015 | 11/30/2015 | 11/30/2015 | | PART |
Andy J. Long
|
|
|
No trackout or discharges outside of Antelope Springs sub. Site perimeter is contained and permanent stormwater infrastructure is installed. DI bags are installed on inlets to capture sediment.
Corrections needed: - street sweeper should do full job on Parsnip Peak - conduct maintenance on sediment sack BMPs - provide designated concrete washout. Cres washing out on vacant lot currently
|
General Inspection | 11/13/2015 | 11/13/2015 | 11/13/2015 | | FAIL |
Evan Jenkins
|
|
|
Street sweeping needs to occur and removal of illegal concrete washout on vacant lot needs to be removed ASAP
|
General Inspection | 10/29/2015 | 10/29/2015 | 10/29/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 10/14/2015 | 10/14/2015 | 10/14/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/29/2015 | 9/29/2015 | 9/29/2015 | | PART |
Andy J. Long
|
|
|
WIP on multiple SFHs in framing phase. No offsite runoff of sediment or other materials. Subdivision DIs with have sediment bag protection. No windblown trash issues.
Correction:
- No designated lined washout. Working with developer and homebuilders to have a washout instead of pouring out on open lots.
|
General Inspection | 9/11/2015 | 9/14/2015 | 9/15/2015 | P | PASS |
Andy J. Long
|
|
|
Subdivision BMPs and perimeter containment are working effectively. No trackout or offsite dischages. SFHs in progress. See BMP violations for Dave Evans construction on ESC15-01019
|
General Inspection | 9/11/2015 | 9/11/2015 | 9/11/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled for Monday for walk through/ washout clean up operation
|
General Inspection | 8/27/2015 | 8/27/2015 | 8/27/2015 | | PART |
Andy J. Long
|
|
|
Individual homes in Antelope Springs are in progress. Multiple contractors have not been using concrete washouts on recent projects.
No significant trackout or discharges to stormwater system. Site needs clean up and housekeeping Will work with individual contractors to clean up litter and uncontained concrete dumps.
|
General Inspection | 8/12/2015 | 8/12/2015 | 8/12/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/28/2015 | 7/28/2015 | 7/28/2015 | | PART |
Evan Jenkins
|
|
|
Curbs and Sidewalks need maintenance. Road and curbs need swept asap. Drop Inlets need to be cleaned out. Contated Pat (Owner). He stated ACHD was just out here a month ago and did sweep and clean drop inlets. I don't see any proof. Stated he needs to get it cleaned up. He stated he will. Contacted Luke Roberts (ACHD) to verify story and left VM. Will check at a later date to ensure site is back in compliance.
|
General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 | | PART |
Andy J. Long
|
|
|
WIP on SFHs in Antelope Springs. Workers parking on pavement to prevent trackout. No trackout.
Hillside and canal bank has vegetated and stabilized nicely along northside.
Correction:
Need to change out DI bags which are near 50% full.
|
General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/11/2015 | 6/11/2015 | 6/11/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 5/27/2015 | 5/27/2015 | 5/27/2015 | | FAIL |
Evan Jenkins
|
|
|
Roads and sidewalks/curbs needs swept or stop work order shall be placed on entire site until corrections are made. 2nd warning
|
General Inspection | 5/12/2015 | 5/12/2015 | 5/12/2015 | | PART |
Andy J. Long
|
|
|
Antelope Springs needs sweeping and inlet maintenance to remove loose sediment.
Bank of Penitiary Canal is in good condition with no rill or gully erosion on banks. SFH homes in progress. Will make request to homebuilders as well. RP - developer is on site monitoring ESC issues regularly.
|
General Inspection | 4/27/2015 | 4/27/2015 | 4/27/2015 | | PART |
Andy J. Long
|
|
|
No hillside erosion or issues around waterfall and ditch channel. Landscaping in progress.
Correction - conduct maintenance on drop inlet filter bags and shovel up accumulated sand & sediment at lips of inlets.
|
General Inspection | 4/10/2015 | 4/10/2015 | 4/10/2015 | | PASS |
Andy J. Long
|
|
|
Antelope Springs SFHs are in progress with multiple contractors. Drop inlets have sediment protection and a significant amount of sand/sediment has collected in gutters.
Need to have street sweeper.
Also working with contractors to provide a lined washout pit or portable washout container.
No trackout or discharges offsite. Penn Canal is flowing, no erosion occuring on banks.
|
General Inspection | 3/26/2015 | 3/26/2015 | 3/26/2015 | | PASS |
Andy J. Long
|
|
|
Antelope Springs SFHs in progress. Storm drains have sediment bags installed, no trackout, site perimeter is intact and containing loose sediment.
|
General Inspection | 3/11/2015 | 3/11/2015 | 3/11/2015 | | PASS |
Andy J. Long
|
|
|
No subdivsion development work occuring at this time. Open parcels are blocked off to prevent trackout. DI's have sediment protection and the site perimeter contains runoff to treatment & retention areas.
Some SFHs currently being landscaped so road is dirty from materials and congestion. Will request that builders have sweeper on a weekend when there isnt so many worker vehicles blocking areas.
Will follow up on individual SFHs
|
General Inspection | 2/24/2015 | 2/24/2015 | 2/24/2015 | | PASS |
Andy J. Long
|
|
|
Site perimeter is contained construction related sediment on site. DIs have inlet protection. No runoff from lots observed. No corrections necessary at Antelope Springs.
|
General Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 | | PASS |
Andy J. Long
|
|
|
WIP on SFHs in Antelope Springs. DI bags are in good conditions, open/unoccupied parcels with mud and puddles have restricted access. No trackout to Parsnip Peak or Warm Springs. Site perimeter is containing sediment and no issues with drainage system.
|
General Inspection | 1/23/2015 | 1/23/2015 | 1/23/2015 | | PASS |
Andy J. Long
|
|
|
Subdivsion BMPS at Antelope Springs are in operating condition. Perimeter of site has retaining rocks and seepage swale to capture and retain runoff.
Some erosoin rills occuring on small portion of slope between upper and lower parcel. Will need to be repaired when mud thaws/dries out.
No sediment or discharges leaving sites.
One SFH needs to sweep up, correction issued seperately see (ESC14-01022)
|
General Inspection | 1/8/2015 | 1/8/2015 | 1/8/2015 | | PASS |
Andy J. Long
|
|
|
Antelope Springs subdivision development has BMPs installed and there is no construction activity for subdivision currently. Individual SFHs in progress with seperate permits. Will work with builders to get Parsnip Peak culdesac cleaned since there is some trackout and loose sediment on hard surfaces.
|
General Inspection | 12/24/2014 | 12/24/2014 | 12/24/2014 | | PASS |
Andy J. Long
|
|
|
WIP. No corrections needed at this time. No new erosion. culdesac is fairly clean. Downstream inlets properly protected.
|
General Inspection | 12/9/2014 | 12/9/2014 | 12/9/2014 | | PASS |
Andy J. Long
|
|
|
BMPs installed at Antelope Springs sub. No discharges offsite or erosion. 1 SFH in progress, workers staying off open parcels with mud on them so there is no major trackout.
No corrections at this time. Site not yet fully stabilized
|
General Inspection | 11/24/2014 | 11/24/2014 | 11/24/2014 | | PASS |
Andy J. Long
|
|
|
WIP on individual parcels. No runoff from site. Snowmelt ponded on open parcels. No trackout to Warm Springs or discharges into the landscaped canal bed/decorative waterway (Penn Canal not currently flowing).
No corrections at this time.
|
General Inspection | 11/7/2014 | 11/7/2014 | 11/7/2014 | | PASS |
Andy J. Long
|
|
|
Antelope Springs is in good condition. Streets were being cleaned during the inspection, perfect timing. No water flowing through canal at this time, no erosion of sediments from lots, and stormdrains have protection. Site has a permanent contaiment barrier wall. No ESC corrections necessary.
|
General Inspection | 10/23/2014 | 10/23/2014 | 10/23/2014 | | PASS |
Evan Jenkins
|
|
|
No esc issues at this time
|
General Inspection | 10/8/2014 | 10/8/2014 | 10/8/2014 | | PASS |
Andy J. Long
|
|
|
Landscaping and irrigation for open areas is currently being installed. Site sediment contaiment perimeteerr and vegetative buffer are in good condition with no evidence of discharge or sediment runoff. The Penn Canal is no longer flowing, so the landscaping will stabilize the north bank before next year's water season.
Checked the outlet of Walling Creek into Boise River downstream from site and other activity in Barber Valley and it is looking very clear with no color, odor or other visible water qualitiy issues.
No corrections at this time.
|
General Inspection | 9/23/2014 | 9/23/2014 | 9/23/2014 | | PASS |
Andy J. Long
|
|
|
No construction activity at Antelope Springs at time of inspection.
Perimeter barrier and fencing is good containment for site. All DI's on Parsnip Peak have filter bag protection and streets and mostly free of sediment. Some minor accumulation of sand in gutters.
The irrgation canal has been routed through the central common area. Water flowing through looked clean and the channel has been lined with rock
No current issues but will inquire with owner about further stabilization or installation of a sediment containment BMP on the north side of the "stream". Water exiting site through culvert is not turbid or have other characteristics of pollution.
SWPPP is managed by Lurre and Kris Jensen.
|
General Inspection | 9/8/2014 | 9/8/2014 | 9/8/2014 | | PASS |
Evan Jenkins
|
|
|
no issues at this time. no work currently in progress during inspection
|
General Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 | | PASS |
Andy J. Long
|
|
|
No activity. No corrections required at Antelope Springs at this time. Site is well contained and banks are stabilizing around Walling Creek.
|
General Inspection | 8/7/2014 | 8/7/2014 | 8/7/2014 | | PASS |
Evan Jenkins
|
|
|
no esc issues at time of inspection no activity
|
General Inspection | 7/23/2014 | 7/23/2014 | 7/23/2014 | | PASS |
Andy J. Long
|
|
|
Antelope Springs is near completion and parcels will soon be survey and recorded. No trackout to Warm Springs, the Walling Creek bank has revegetated/stabilized.
Discussed project with RP/developer Pat and he stated this evening a sweeping is doing the culdesac and the stretch of Warm Springs in front the development.
No corrections if sweeping is completed this week.
|
General Inspection | 7/8/2014 | 7/8/2014 | 7/8/2014 | | PART |
Evan Jenkins
|
|
|
landscapers/pressure irrigation outfit has caused some sediment to enter the road and curb that needs to be swept up
|
General Inspection | 6/20/2014 | 6/20/2014 | 6/20/2014 | | PASS |
Evan Jenkins
|
|
|
No ESC Issues at time of inspection
|
General Inspection | 6/5/2014 | 6/5/2014 | 6/5/2014 | | PASS |
Andy J. Long
|
|
|
Antelope Springs road has been paved and sidewalk poured. Perimeter fence/sediment containment is in good condition. Some minor work ongoing. No corrections. No hydroseeding bank and stormwater features yet.
|
General Inspection | 5/21/2014 | 5/21/2014 | 5/21/2014 | | PASS |
Andy J. Long
|
|
|
Road is now paved. Working on the manholes for sewer and installing sidewalk along Warm Springs. Concrete trucks using lined washout on site.
Warm Springs should be swept along the frontage of the development when they clean the new road.
Site perimeter is well contained.
|
General Inspection | 5/6/2014 | 5/6/2014 | 5/6/2014 | | PASS |
Andy J. Long
|
|
|
Installing curb along side Warm Springs. Large lined washout pit is provided on the upper staging area for the work. Road into development has been compacted, looks like it will soon be paved. Site has good vegetative and structural buffer. No corrections at this time.
|
General Inspection | 4/17/2014 | 4/18/2014 | 4/18/2014 | A | PASS |
Andy J. Long
|
|
|
Curbing and streets are in process of installation. Lurre Construction has water truck on site for dust. A good lined washout has been built up above the site to keep clear from creek/ditch. Stormwater faciltiies not yet connected but will need to protect DI at entrance. Will check next inspection or once road is complete.
|
General Inspection | 4/17/2014 | 4/17/2014 | 4/17/2014 | | CANC |
Andy J. Long
|
|
|
rescheduled for 4/18
|
General Inspection | 4/2/2014 | 4/2/2014 | 4/2/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/18/2014 | 3/18/2014 | 3/18/2014 | | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Construction entrance looks good. Site is preparing to complete installation of utilities. No trackout. Perimeter is containing sediment to site.
|
General Inspection | 3/3/2014 | 3/3/2014 | 3/3/2014 | | PASS |
Evan Jenkins
|
|
|
No Activity at time of inspection
|
General Inspection | 2/14/2014 | 2/14/2014 | 2/14/2014 | | PASS |
Andy J. Long
|
|
|
No activity. Construction is post poned until weather conditions improved. No trackout or discharges from site.
|
General Inspection | 1/30/2014 | 1/30/2014 | 1/30/2014 | | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Perimeter retaining wall and buffer are being maintained. No trackout to Warm Springs.
Approved.
|
General Inspection | 1/15/2014 | 1/15/2014 | 1/15/2014 | | PASS |
Andy J. Long
|
|
|
Conducted full perimeter walk around. Area of disturbance clearly delineated by berms and concrete blocking that will serve as foundation for fence. Vegetatative barrier was kept in tact outside of concrete blocking.
Met contractor/owner Pat on-site and discussed BMPs. Construction entrance was refilled 1/14; weekly inspections for SWPPP performed by Syman Co.
No corrections at this time.
|
General Inspection | 12/31/2013 | 12/31/2013 | 12/31/2013 | | PASS |
Andy J. Long
|
|
|
No activity. Perimeter BMPs installed. No track out observed.
|
General Inspection | 12/13/2013 | 12/13/2013 | 12/13/2013 | | PASS |
Andy J. Long
|
|
|
No construction activity at time of inspection due to poor weather. No violations observed. BMPs installed around perimeter. Subdivision development and infrastructure still in progress.
|
General Inspection | 11/28/2013 | 11/28/2013 | 11/29/2013 | | CANC |
Evan Jenkins
|
|
|
Holiday
|
General Inspection | 10/14/2013 | 10/14/2013 | 10/14/2013 | P | FAIL |
Evan Jenkins
|
|
|
Correction Notice Posted: Contacted Kris Jensen via phone twice today describing the issue of track out. BMP Violation: No Construction Entrance. Install Construction Entrace and Sweep Road Immediately
|
Routing - Erosion and Sediment | 9/11/2013 | | 9/12/2013 | | DONE |
Jason C. Taylor
|
|
|
Dewatering plan approved. JCT
|
Site Preparation | 9/10/2013 | 9/10/2013 | 9/11/2013 | P | PASS |
Eric Strole
|
|
|
All bmp's in place, sign posted and dewatering is all maintained on site.
|
Additional plans submitted | | | 9/11/2013 | | DONE |
Tisha Gallop
|
|
|
submitted two copies of dewatering plan and narrative; taken to Jason Taylor
|
Issue & PRINT permit COM | | | 8/19/2013 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 7/11/2013 | | |
|
|
|
|
Routing - Erosion and Sediment | 7/11/2013 | | 7/11/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|